Crossrail clung to ‘unrealistic’ timeline as contract renegotiations cost an extra £2.5bn, NAO reports

Crossrail “clung to an unrealistic view” throughout its delivery and has damaged public value, but is now “past the point of no return” and must focus on meeting its new target, a report from the National Audit Office (NAO) has said.

Whitehall’s spending watchdog said it is impossible to determine the overall value for money for taxpayers until Crossrail is completed, which transport bosses revealed last week would be between October 2020 and March 2021.

Following up on a damning report from the Public Accounts Committee (PAC), the NAO has further identified how the flagship programme descended into difficulty which has so far led to £2.8bn of additional ‘bailout’ financing and a two-year delay.

A compressed schedule, the loss of downward pressure on costs, and the absence of an achievable plan set against a “can do” attitude made the delivery plan, which was dominated by a competition date of December 2018, unrealistic.

The NAO said the delivery approach, delays to contracts, and the decision to set and stick to the original opening date had increased risks, and there was a large gap in Crossrail’s understanding of these delivery risks.

Changes required to the design and to contractors’ delivery schedules increased costs on most of the 36 main contracts, which resulted in increased costs of around £2.5bn between 2013 and 2018.

Pressure has continued to escalate through the end of 2018, with the forecasted final cost of the contract to install track and key tunnel systems increased by 80%, and the NAO said Crossrail made several decisions which drove unnecessary costs.

But the report stated that with nearly £16bn already spent, trains ordered and tunnelling long since completed, Crossrail is “past the point of no return” and must now focus on meeting its new targets.

Amyas Morse, the head of the NAO, said today: “Throughout delivery, and even as pressures mounted, Crossrail Ltd clung to the unrealistic view that it could complete the programme to the original timetable, which has had damaging consequences.

“DfT and TfL must support the new Crossrail Ltd executive team to get the railway built without unrealistic cost or time expectations.

“While we cannot make an overall assessment of value for money until Crossrail is complete, there have been a number of choices made in the course of this project that have clearly damaged public value.”

Crossrail chief executive Mark Wild commented: “We take the views of the National Audit Office very seriously and will be reviewing their recommendations carefully.

“I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. A new leadership team and enhanced governance structure has been put in place to strengthen the Crossrail programme and put the project back on track.”

Comments

There are no comments. Why not be the first?

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Grand Central plans new rail route from Blackpool to London from spring 2020

25/06/2019Grand Central plans new rail route from Blackpool to London from spring 2020

Grand Central will run a new route from Blackpool to London from spring 2020, the train operator announced today. The new InterCity services... more >
Transport for Wales awards first ECI contracts for £700m South Wales Metro

25/06/2019Transport for Wales awards first ECI contracts for £700m South Wales Metro

Transport for Wales (TfW) has awarded three companies to begin preparatory works on the £738m South Wales Metro, the organisation announced... more >
Increasing passenger confidence and accessibility with the Rail Delivery Group

25/06/2019Increasing passenger confidence and accessibility with the Rail Delivery Group

The Rail Delivery Group plans to make travelling by train easier than ever before by making trains and stations more accessible and developing a ... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey’s commercial account director, Anna Delvecchio, for her insight into what the Rail Sector Deal means for the rail industry and its supply chain. Anna started her career as an apprentice at the age o... more >
read more blog posts from 'the sleeper' >

comment

Increasing passenger confidence and accessibility with the Rail Delivery Group

25/06/2019Increasing passenger confidence and accessibility with the Rail Delivery Group

The Rail Delivery Group plans to make travelling by train easier than ever before by making trains and stations more accessible and developing a ... more >
Diversity, inclusion and marking 100 years of Women in Engineering

24/06/2019Diversity, inclusion and marking 100 years of Women in Engineering

100 years of Women in Engineering, and transforming the future too One hundred years on from the birth of the Women in Engineering Society (... more >
Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

20/06/2019Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

RTM talks exclusively to one of the rising stars of the industry and Transport’s Woman of the Year 2018, Anna Delvecchio. Amey’s... more >
Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

By Ewan Quayle, Rail Technology Magazine Reporter Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on R... more >