HS2

03.05.19

Crossrail clung to ‘unrealistic’ timeline as contract renegotiations cost an extra £2.5bn, NAO reports

Crossrail “clung to an unrealistic view” throughout its delivery and has damaged public value, but is now “past the point of no return” and must focus on meeting its new target, a report from the National Audit Office (NAO) has said.

Whitehall’s spending watchdog said it is impossible to determine the overall value for money for taxpayers until Crossrail is completed, which transport bosses revealed last week would be between October 2020 and March 2021.

Following up on a damning report from the Public Accounts Committee (PAC), the NAO has further identified how the flagship programme descended into difficulty which has so far led to £2.8bn of additional ‘bailout’ financing and a two-year delay.

A compressed schedule, the loss of downward pressure on costs, and the absence of an achievable plan set against a “can do” attitude made the delivery plan, which was dominated by a competition date of December 2018, unrealistic.

The NAO said the delivery approach, delays to contracts, and the decision to set and stick to the original opening date had increased risks, and there was a large gap in Crossrail’s understanding of these delivery risks.

Changes required to the design and to contractors’ delivery schedules increased costs on most of the 36 main contracts, which resulted in increased costs of around £2.5bn between 2013 and 2018.

Pressure has continued to escalate through the end of 2018, with the forecasted final cost of the contract to install track and key tunnel systems increased by 80%, and the NAO said Crossrail made several decisions which drove unnecessary costs.

But the report stated that with nearly £16bn already spent, trains ordered and tunnelling long since completed, Crossrail is “past the point of no return” and must now focus on meeting its new targets.

Amyas Morse, the head of the NAO, said today: “Throughout delivery, and even as pressures mounted, Crossrail Ltd clung to the unrealistic view that it could complete the programme to the original timetable, which has had damaging consequences.

“DfT and TfL must support the new Crossrail Ltd executive team to get the railway built without unrealistic cost or time expectations.

“While we cannot make an overall assessment of value for money until Crossrail is complete, there have been a number of choices made in the course of this project that have clearly damaged public value.”

Crossrail chief executive Mark Wild commented: “We take the views of the National Audit Office very seriously and will be reviewing their recommendations carefully.

“I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. A new leadership team and enhanced governance structure has been put in place to strengthen the Crossrail programme and put the project back on track.”

Comments

There are no comments. Why not be the first?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >