London Underground and TfL

03.05.19

Crossrail clung to ‘unrealistic’ timeline as contract renegotiations cost an extra £2.5bn, NAO reports

Crossrail “clung to an unrealistic view” throughout its delivery and has damaged public value, but is now “past the point of no return” and must focus on meeting its new target, a report from the National Audit Office (NAO) has said.

Whitehall’s spending watchdog said it is impossible to determine the overall value for money for taxpayers until Crossrail is completed, which transport bosses revealed last week would be between October 2020 and March 2021.

Following up on a damning report from the Public Accounts Committee (PAC), the NAO has further identified how the flagship programme descended into difficulty which has so far led to £2.8bn of additional ‘bailout’ financing and a two-year delay.

A compressed schedule, the loss of downward pressure on costs, and the absence of an achievable plan set against a “can do” attitude made the delivery plan, which was dominated by a competition date of December 2018, unrealistic.

The NAO said the delivery approach, delays to contracts, and the decision to set and stick to the original opening date had increased risks, and there was a large gap in Crossrail’s understanding of these delivery risks.

Changes required to the design and to contractors’ delivery schedules increased costs on most of the 36 main contracts, which resulted in increased costs of around £2.5bn between 2013 and 2018.

Pressure has continued to escalate through the end of 2018, with the forecasted final cost of the contract to install track and key tunnel systems increased by 80%, and the NAO said Crossrail made several decisions which drove unnecessary costs.

But the report stated that with nearly £16bn already spent, trains ordered and tunnelling long since completed, Crossrail is “past the point of no return” and must now focus on meeting its new targets.

Amyas Morse, the head of the NAO, said today: “Throughout delivery, and even as pressures mounted, Crossrail Ltd clung to the unrealistic view that it could complete the programme to the original timetable, which has had damaging consequences.

“DfT and TfL must support the new Crossrail Ltd executive team to get the railway built without unrealistic cost or time expectations.

“While we cannot make an overall assessment of value for money until Crossrail is complete, there have been a number of choices made in the course of this project that have clearly damaged public value.”

Crossrail chief executive Mark Wild commented: “We take the views of the National Audit Office very seriously and will be reviewing their recommendations carefully.

“I share the frustration of Londoners that the huge benefits of the Elizabeth Line are not yet with us. A new leadership team and enhanced governance structure has been put in place to strengthen the Crossrail programme and put the project back on track.”

Comments

There are no comments. Why not be the first?

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Ep 8 Safely shaping a sustainable railway, Martin Frobisher

20/02/2020Ep 8 Safely shaping a sustainable railway, Martin Frobisher

Martin Frobisher, Group director, Safety, Technical & Engineering and Network Rail, joins us in the RTM Podcast room to discuss the renewable... more >
Southend Victoria line disruption following a landslip at Billericay

20/02/2020Southend Victoria line disruption following a landslip at Billericay

Railway tracks on the Southend Victoria line, between Billericay and Wickford, have been damaged following a landslip. Ballast, the stones that h... more >
HS2’s latest designs for Old Oak Common Station revealed

20/02/2020HS2’s latest designs for Old Oak Common Station revealed

HS2 Ltd yesterday (Feb 19th) revealed designs for Old Oak Common Station, as part of the Schedule 17 submission to the Old Oak and Park Royal Dev... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

14/11/2019Maximising efficiency requires investment in data, but it’s rewards for rail could be extensive

Rail Technology Magazine’s Matt Roberts explains the significant role data can play within the future development of the rail industry. Standing as a cornerstone of the UK transport network, the rail industry is forever striving to innovate and maximise efficiency in all aspects of i... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Ep 8 Safely shaping a sustainable railway, Martin Frobisher

20/02/2020Ep 8 Safely shaping a sustainable railway, Martin Frobisher

Martin Frobisher, Group director, Safety, Technical & Engineering and Network Rail, joins us in the RTM Podcast room to discuss the renewable... more >