27.07.17
GOBLIN electrification on track for January 2018 completion
Network Rail has this week confirmed that the GOBLIN electrification project is expected to be completed in January 2018 ahead of new trains arriving in spring.
The project aiming to electrify the line on the Overground between Gospel Oak and Barking was originally due to be finished by June this year, but this was pushed back due to multiple issues with design and cables.
But now, it has been confirmed that the end is on the horizon as works will be finished in January next year, thus enabling testing of the new electric trains and driver training to begin.
Passenger services will then begin to roll out from spring – diesel services will continue to run as normal until they are replaced by the new double-length trains.
Weekend closures will take place from 29 July to 10 September, and talks are ongoing between Network Rail, TfL and operators to finalise agreements for further weekend closures later on in the year.
Longer closures are proposed to take place between 17 September and 22 October, and again from 27 November until 14 January 2018.
“The Gospel Oak to Barking line is set to benefit from a transformational upgrade with better services provided by a new fleet of longer electric trains, doubling the current capacity,” said Meliha Duymaz, route managing director at Network Rail.
“This project has not been without its difficulties and we’d like to apologise for the continued disruption and thank both passengers and neighbours for their patience while we finish our work.
“We still have a lot to do but with a new team in place to finish off the project, I’m confident that the immense benefits of this once-in-a-lifetime investment will be realised in the months ahead, and the benefits enjoyed for years to come.”
Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.