Latest Rail News

23.01.15

Stop-start progress on ‘essential’ Walsall electrification bridge rebuilds

Network Rail is to complete rebuild work on two ‘essential’ bridges as part of the electrification of the railway between Walsall and Rugeley Trent Valley by the spring, but work on a third has been delayed until later this year. 

All three bridges are being rebuilt to accommodate overhead power lines underneath as part of the £30m electrification of the Chase Line. 

Work started in autumn 2014 to rebuild the North Street bridge, with completion due in late spring 2015. 

The construction of a new bridge in Central Drive, however, was stopped late last year while the potential impact of former mineshafts was assessed. 

Following the investigations, work will resume on 26 January to complete the construction by late spring. A road closure will be in place, but pedestrian access will be maintained throughout the work. 

But work to rebuild a third bridge at Park Street in Walsall town centre has been rescheduled until October 2015 after complications to remove the existing structure were revealed. 

Work on the Park Street bridge had resumed last week after a temporary stop over Christmas and the New Year to minimise the impact on the local area. But engineers discovered the structure, which dates back to the 1930s, was different to the original plans, which means the planned removal of the structure by crane has to be reassessed, said Network Rail.

Originally, the process for rebuilding the bridge was to be completed in four stages to allow Park Street to remain open for business, with the project expected to be complete by July 2015. 

However, as a result of the reschedule, work will now take place between October and spring 2016. Network Rail is confident, though, that new time will not impact on the overall electrification project between Walsall and Rugeley Trent Valley which will be completed by the end of 2017. 

Liam Sumpter, area director for Network Rail, said: “Electrification provides a greener, faster and more reliable railway, providing a better service to passengers. A significant amount of work is required to upgrade the railway and much is already underway or completed as part of our investment. 

“Replacing these bridges is essential to allow the line to be electrified and while there will be disruption while the upgrades are completed the end result will be a better railway for Walsall and the wider West Midlands.” 

(Central Drive image: c. Network Rail)

Tell us what you think – have your say below, or email us directly at [email protected]

Comments

There are no comments. Why not be the first?

Add your comment

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >