Latest Rail News

20.11.15

Network Rail admits it was ‘overly ambitious’ with CP5 projects

Network Rail has admitted it was “overly ambitious” in what it could achieve with the funds and resources available in CP5. 

Responding to the Public Accounts Committee’s (PAC’s) report into Network Rail’s investment programme, the infrastructure owner stated that its “understanding of how best to plan and deliver major new electrification schemes was not good enough”. 

According to the PAC, the DfT, Network Rail and ORR agreed to an “unrealistic” programme of rail investment for CP5 that contained “too much uncertainty” on the costs of many large projects when it was signed off. 

During the Committee’s inquiry, Mark Carne also revealed that the expected cost for Great Western electrification had increased by up to £1.2bn from the £1.6bn agreed in 2014. This means the cost range is now between £2.5bn and £2.8bn. 

The MPs said it is “not clear” whether the cost escalation is due to Network Rail inefficiency, ORR lacking a full understanding of the work needed, or a combination of both. 

The Committee is now calling for Network Rail it to embed “much tighter” project planning, costing and cost control throughout the organisation. It must also be “clearer” with the DfT about what can and cannot be afforded. 

Following the “unacceptable” cost increase on Great Western electrification, it has been recommended that the DfT and Network Rail publish an updated schedule and cost forecast for the project – along with a full account of what has caused the cost increases to date and proposals for controlling future costs. 

PAC added that there is still “far too much uncertainty” on costs and eventual delivery dates for the other two major rail electrification programmes in the 2014-2019 programme: TransPennine and Midland Main Line, which have now been delayed into CP6. 

Sir Peter Hendy’s review of these and the other rail enhancement planned for CP5, which is to be published towards the end of this year, will bring more bad news on costs, said the MPs. 

A Network Rail spokesperson told RTM: “It is clear that we, as an industry, were overly ambitious about what could be accomplished with the funds and resources available to deliver the high levels of investment which will enable our railway to continue to cater for growing numbers of passengers and support economic growth. 

“Network Rail has successfully delivered over 5,000 projects over the past five years, but our understanding of how best to plan and deliver major new electrification schemes was not good enough. We have now made significant changes to the way we plan and deliver our investment programme, which will see schemes progress only once they are sufficiently developed that a reliable cost estimate can be established. 

“Sir Peter Hendy’s report on the deliverability of the current investment plan will be published later this month.” 

Additionally, for the next planning round of rail investment, and in all future investment planning, the government must assure itself that its plans can be delivered, stated the Committee. It has now called on the DfT and ORR to “assess and explain how uncertainty in key projects could affect the plan’s overall costs and schedule” for all rail spending decisions. 

PAC added that the five-year rail investment planning and funding model, which is appropriate for ongoing operations, maintenance and renewals, is “not adequate” for major enhancement work such as the current electrification schemes. 

In respect of this, the MPs want the ORR and DfT to put in place “sharper accountability arrangements” for major enhancement projects, such as the Great Western Main Line electrification, and agree principles on when it is appropriate to fund and manage these projects outside the five year rail funding cycle. 

A DfT spokesperson said: “We are proud to have a hugely ambitious investment programme, but agree that lessons should be learned on all sides. 

“We are committed to seeing the £38bn programme through and delivering the railway passengers deserve. That’s why the secretary of state asked Dame Colette Bowe to look at the lessons learned and make recommendations on what can be done better in future, and why Sir Peter Hendy is developing proposals to get the rail upgrade programme back on track and ensure it is both affordable and deliverable. Both reports will be published later in the autumn. We will respond to the PAC in due course.”

Comments

Huguenot   20/11/2015 at 17:10

On GW electrification, even when Network Rail did think it could achieve it to the original timescale, why didn't it concentrate on one route first, e.g. London to Bristol TM via Bristol Parkway, instead of pressing ahead on several fronts including the Chippenham route and the Berks & Hants? At least then it might have achieved something for the IEP to run on. Instead, the taxpayer is going to be paying for the Class 800s to be languishing in sidings whilst the wires go up.

Andy Ellis   23/11/2015 at 08:28

Network Rail, and the Government's “understanding of how best to plan and deliver major new electrification schemes was not good enough” surprise, surprise! That's because they haven't done any on anywhere near the scale of Midland Main Line, never mind GWML, for 30 years. When East Coast Main Line electrification was finished in the 1980's the Engineers said give us a rolling programme and let us carry on! Privatisation, through separation of trains and track destroyed any coherent business plan for electrification as all the cost sits with Network Rail and all the benefit sits with the train operating companies which is why it has taken so long to get electrification going again. Then to try to do it all at once was a nonsense. A railway is a long term high investment business and its funding cannot be run to short term political time scales. This was why British Rail could never deliver it's five and ten year plans, government kept hold of the purse strings and only released funds on a yearly basis, we cannot afford to go back to those days either! Similarly HS2 has been totally miss sold by the politicians, it is not about journey times, it is the natural expansion and growth of the UK rail network to modern standards. The message that should have been communicated is how many miles of major trunk roads and motorways have been built in the last 50 years and how many miles of mainline railway have been built over the same period? I would rather have a railway at the bottom of my garden than a motorway.

Add your comment

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >