Latest Rail News

07.04.16

Gospel Oak to Barking Line to close for eight months for electrification upgrades

Closures on the Gospel Oak to Barking Line are due to start from June to allow for electrification upgrades.

From 4 June to 25 September the South Tottenham to Barking line will close and the South Tottenham to Gospel Oak line will only run at weekends, and the full Gospel Oak to Barking line will then close from 26 September to February 2017. TfL will provide a replacement bus service.

Once complete, the upgrades will allow TfL to run four-carriage electric trains instead of the current two-carriage diesel models from January 2018.

Richard Schofield, Network Rail’s route managing director, said: “This investment will transform the service on this route, doubling capacity with cleaner, quieter electric trains and is a key element of our wider Railway Upgrade Plan.”

The improvement works will include installing overhead wires, building three new switching stations, lowering four sections of track, rebuilding four bridges and modernising six, and lengthening platforms and enhancing stations to accommodate longer trains.

Network Rail has been working on the foundations for the structures that will carry the overhead wires since October. The scheme is being funded by £25m from TfL and £90m from the DfT.

The National Infrastructure Commission said in a recent report that extensive investment in London’s railways, including Crossrail 2, is needed to accommodate the growing population of the capital, which will become a ‘megacity’ of 10 million people by 2033.

To keep members of the public updated about the closures, TfL and Network Rail are organising drop-in sessions at the affected stations and sharing information via e-mail alerts, Twitter, posters and station announcements.

Mike Stubbs, TfL’s director of London Overground, said: “We recognise that there will be disruption to customers while the upgrade work is carried out and I'd like to thank them for their patience in advance.”

He said that TfL would work with Network Rail to try to reduce the closure period.

Comments

Andrew Gwilt   07/04/2016 at 23:43

Plus the electrification to Barking could also kick start the London Overground extension to Barking Riverside and even to Abbey Wood if necessary. The electrification could be completed by late February or early March next year if it doesn't get held up.

GW   09/04/2016 at 22:39

Another example of lazy engineering by Network Rail. No thought about those who use the route everyday and the inconvenience caused to the users.

Paul   11/04/2016 at 15:12

@Andrew Gwilt Abbey Wood isn't going to happen anytime soon, as the nowagreed barking riverside extension design has no provision for it, and will require a complete demolition and rebuild to make a river crossing possible.

Andrew Gwilt   13/04/2016 at 09:33

Properly DLR extension could be extended to Abbey Wood & Dagenham Dock would be ideal as London Overground extended to Barking Riverside would be the terminus of the London Overground GOBLIN (Gospel Oak-Barking line) or to be renamed as GOBRLN (Gospel Oak-Barking Riverside line) once the extension to Barking Riverside is completed.

John Barnes   04/05/2016 at 08:10

This is completely unacceptable. You can't close an entire line for 6 months. There are many other options, including a shuttle line along the stations which are currently not being worked on. This is lazy and poorly thought out.

Add your comment

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >