Construction of HS2's twin rail tunnels into central London has passed a major milestone, with the project reaching the halfway point on the route to the new high-speed station at Euston.
The achievement marks significant progress on one of the railway's most complex engineering challenges, as giant tunnel boring machines (TBMs) Karen and Madeleine continue carving out the twin-bore tunnels between Old Oak Common and Euston.
Launched from HS2’s future super hub at Old Oak Common in January and March 2026 respectively, the two 1,624-tonne machines have been advancing at an average rate of around 16 metres per day. As of 17 November, both TBMs had reached the area between West Hampstead and Kilburn High Road stations.
The tunnels are a critical element of the HS2 programme, connecting the railway into its ultimate London terminus. Once operational, the new station at Euston will enable long-distance high-speed services to transfer from the West Coast Main Line, freeing up capacity on the existing network for additional passenger and freight services between London and Birmingham and supporting economic growth along the corridor.
Working around the clock, the machines are being operated by Skanska Costain STRABAG Joint Venture (SCS JV), HS2 Ltd's London tunnels contractor. The 4.5-mile tunnelling programme is expected to generate around 1.5 million tonnes of excavated material during construction.
In addition to excavation work, the TBMs are simultaneously installing the tunnel lining using 48,294 precast concrete segments manufactured in Hartlepool, further demonstrating the project's extensive UK supply chain footprint.

Industry Leaders Welcome Progress
Rail Minister Lord Hendy said:
“This achievement marks another important step in delivering HS2 into the heart of London.
“The progress made by the tunnelling teams shows the momentum being built on the project as we work to deliver a railway that provides greater capacity, faster journeys and long-term benefits for growth, jobs and homes."
HS2 Ltd chief executive Mark Wild said:
“Reaching the halfway mark for building the programme’s last deep bored tunnel is a magnificent achievement by everyone involved. Their work driving the high speed line into central London is fundamental to the long term ambition of increasing the prosperity of the area around Euston. I wish everyone a safe journey to their final destination.
“HS2 Ltd is now in the last phases of a root and branch full-programme reset that will safely deliver the railway at lowest reasonable cost. The new line we’re driving to Euston will complement the existing station and the West Coast Mainline, providing fast and reliable long distance journeys with its new capacity.”
Skanska Costain STRABAG Delivery Lead, Eddie Edmonds said:
“It’s a fantastic technical achievement to be 50% of the way through construction of HS2’s final running tunnels. Months of meticulous planning and preparation have brought us to this point and into the final leg of the journey. This progress is down to that preparation and the skill, expertise and diligence of the teams working not only on the tunnel boring machines, but also those supporting the operation and carrying out the many other tasks essential to its success. The fact that this complex operation is taking place up to 50 metres beneath London makes it an even greater achievement.”
Tunnelling Set for Completion in 2027
Both tunnel boring machines are expected to complete their journeys during 2027, emerging underground near the planned Euston station approach.
Once tunnelling is complete, major components of the machines will be removed. The 8.53-metre-diameter cutterheads will be extracted from the Euston Cavern, while the outer steel shields will remain underground and be permanently grouted behind the tunnel lining.
The milestone also underlines the wider ambition for the regeneration of the Euston area. The Government-backed Euston Delivery Company will oversee the development of the integrated transport hub, bringing together the new HS2 station, redevelopment of the existing Network Rail station, London Underground upgrades and wider commercial development across the Euston campus.
With the tunnels now more than halfway complete, HS2's final deep-bored tunnel section has entered its closing stages, bringing the long-term vision of high-speed rail connectivity into central London another step closer.