HS2 has begun a major rail freight operation at Euston, with up to 170,000 tonnes of excavated material set to be removed by train as construction progresses on the new high-speed station.

During a visit to the site on Monday, Rail Minister Lord Hendy saw first-hand how rail freight is helping to reduce the impact of construction activity on local communities while supporting the delivery of one of the UK's most significant infrastructure projects.

HS2's station construction partner, the Mace Dragados Joint Venture (MDJV), has started the bulk excavation phase of the Euston station site. The work involves digging to a depth of around seven metres to create space for the future HS2 platforms.

To support the programme, HS2 has established a dedicated loading facility adjacent to the disused Track 17 at Euston station. Excavated material is being loaded directly onto freight trains and transported to Forders Sidings in Bedfordshire, where it will be reused as part of the Stewartby Brickworks development.

The initiative has been carefully planned in collaboration with Network Rail, GB Railfreight, and wider rail industry partners to ensure freight services can operate alongside passenger services at one of the UK's busiest rail hubs.

The environmental and community benefits are substantial. By moving material by rail rather than road, the programme is expected to eliminate more than 10,000 HGV movements across Euston and wider London.

Rail Minister, Lord Hendy said:

"Moving this soil by rail will mean thousands fewer HGV journeys through the streets around Euston, helping to reduce disruption for local people, improve road safety and cut carbon emissions.

"This is part of the real progress we are making on HS2. All 23 miles of the tunnels between Old Oak Common and Birmingham have now been dug and more than 80% of the project’s major structures are under construction or complete. Under new leadership, HS2 Ltd is delivering more for every pound having moved 20 million cubic metres of earth - 16% ahead of plan.”

Successful Trials Pave the Way

The rail freight operation follows a successful trial programme that ran between February and September 2026, during which approximately 35,000 tonnes of material were transported from Euston by rail.

The trials demonstrated that trains could carry more material than initially anticipated while operating reliably alongside passenger services.

A further 135,000 tonnes is scheduled to be removed over the next ten months, with up to two GB Railfreight services per day operating during the main excavation phase.

Each train can transport around 715 tonnes of material, equivalent to approximately 45 HGV loads, significantly reducing pressure on local roads.

Commitment to Reducing Community Impact

Andy Swift, Stations Delivery Director, HS2 said:

"We are committed to reducing the impact of our work on the communities around Euston. Moving material by rail is one of the most effective ways we can reduce the number of construction vehicles using local roads.

"Delivering this programme has required careful planning with Network Rail, GB Railfreight and our construction partners. That collaboration will allow us to move up to 170,000 tonnes of material by rail while passenger services continue to operate at Euston.”

Camden Council Welcomes the Initiative

The move has also been welcomed by Camden Council, which has long advocated for greater use of rail freight to support major construction projects in the borough.

Cllr James Slater, Leader of Camden Council, said:

"For many years, Camden has called for construction materials to be removed from Euston by rail, so it is excellent to see this now being delivered at scale. Taking more than 10,000 lorries off Camden's roads is a significant achievement that will reduce disruption for our residents and businesses, improve air quality and help cut carbon emissions.

"This is exactly the kind of practical measure that will make a real difference to our communities living alongside the Euston site and on routes in and out of our borough. As construction progresses, we want to see every opportunity taken to further increase the amount of material moved by rail, and we will continue supporting HS2 and partners to explore all options to maximise the benefits that this measure can deliver for our residents.”

Major Carbon Reduction Benefits

The environmental case for rail freight remains compelling. According to HS2, rail freight can produce up to 76% fewer CO₂ emissions than road haulage when transporting the same weight of material over the same distance.

The Euston operation forms part of HS2's wider strategy to maximise use of the existing railway network throughout construction. Similar freight movements have already delivered aggregates into sites in Buckinghamshire and Birmingham, transported tunnel segments to West Ruislip and Willesden, and removed millions of tonnes of excavated material from construction sites around Old Oak Common.

Industry Collaboration Key to Success

Patrick Cawley, Director for On Network Works at Network Rail and HS2, said:

"We’re proud to be working with HS2 and our rail industry partners to help make this programme possible. It’s been a real collaborative effort across many different teams to safely accommodate these freight trains alongside the day-to-day operation of one of Britain’s busiest stations, while keeping passengers moving.

"It’s also a great example of what the railway can do best. Moving more materials by rail means fewer lorries on local roads and lower carbon emissions, and we’re pleased that the existing railway is playing such an important role in supporting the delivery of HS2 at Euston.”

Each freight service will operate with two locomotives and up to 12 wagons, maximising carrying capacity while ensuring efficient loading and unloading operations.

Track 17 is currently expected to remain available until early 2029, with HS2 continuing to work alongside the Euston Delivery Company and other stakeholders to explore further opportunities for rail freight across the wider Euston development programme.

Image credit: Network Rail

Mag

RTM Issue 151

HS2 Completes First Six Underground Platforms at Old Oak Common Station

Focusing on the latest developments, innovations, and policy impacts in the UK rail industry, with a particular emphasis on sustainability, infrastructure upgrades, and future technological advancements.

More articles...

View all
TCR

TransCityRail

Scotland \ 04.06.26
Mids \ 09.07.26
South \ 15.10.26
North \ 05.11.26

TransCityRail is a series of regional, interactive and insightful events across the country bringing together leaders, collaborators, problem solvers and innovators in a creative and invigorating way.
 

This series of events supports and informs the whole of the rail industry and connects suppliers with buyers, specifiers, leaders and decision-makers looking to procure a wide variety of innovative products and services for their region.

Rail Technology Magazine Podcast

Listen to industry leaders on everything within rail

Whether it's the latest advancements in rail technology, policies, innovations, or the challenges facing the rail industry providers, we cover it all.

 

Join us as we engage with top rail professionals, industry leaders, and policy experts to bring you insightful conversations that matter.