Construction of HS2’s new Coventry Road overbridge near Bickenhill has reached its halfway point, marking a significant step forward in the delivery of the high-speed railway’s approach to Interchange Station.
Over the past 11 months, engineers working for HS2’s construction partner, Balfour Beatty VINCI (BBV), have successfully completed the first half of the new A45 Coventry Road overbridge. The vital structure is being built in two stages to ensure traffic can continue flowing while construction progresses, helping to minimise disruption on one of the region’s busiest strategic routes.
The bridge will ultimately carry the A45 over four HS2 railway tracks as trains approach the new Interchange Station, located approximately one mile away.
Complex Engineering Beneath a Live Highway
Using an innovative top-down construction technique, engineers excavated around 7,500 tonnes of earth from beneath the existing carriageway before installing 46 piles extending up to 23 metres deep. These foundations support the new 2,000-tonne bridge deck, which will span 37 metres across the future railway corridor.
During the summer, the project team installed 13 pre-stressed pre-cast concrete beams, forming the bridge deck structure, alongside 13 parapet units on the first section of the crossing.
With waterproofing and highway works nearing completion, the eastbound side of the new structure will soon be opened to traffic, allowing work to begin on the second phase.
Traffic Switch Planned
HS2 and National Highways are preparing for a series of overnight and weekend closures to facilitate the transfer of traffic onto the newly completed eastern section of the bridge.
Once the switchover is complete, motorists will begin using a temporary carriageway alignment while construction continues on the remaining half of the structure.
Maintaining Traffic Flow During Construction
Paul Marshall, Head of Delivery at HS2 Ltd said:
“Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway."
“During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we’ll ensure that access to businesses and properties is maintained.
“I’d encourage motorists to familiarise themselves with the diversion routes and thank them for their patience.”
Next Phase Begins in the New Year
Construction on the western half of the bridge is scheduled to begin in the new year and will follow a similar build sequence.
Meanwhile, excavation work beneath the structure will continue as engineers create the railway corridor that will eventually accommodate four tracks feeding into Interchange Station. The station itself will feature four platforms arranged across two 425-metre-long platform islands, serving high-speed services across the UK.
Important Structure on the HS2 Route
The Coventry Road crossing forms a key component of the HS2 route through the West Midlands and is one of several major highway interfaces required to accommodate the new railway.
Richard Husbands, Balfour Beatty VINCI’s Project Manager said:
“The Coventry Road overbridge is one of the key crossings on this part of the route, allowing the railway to pass under the A45 as it approaches Interchange Station.”
“Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project.”
“The programme we’re working to has been designed to minimise disruption for motorists and local communities as much as possible. We’re grateful for everyone’s continued patience, as we move to the next phase of construction.”
Looking Ahead to 2028
Above-ground construction activity is expected to continue throughout 2027, with the bridge becoming structurally complete by the end of the year.
Following completion of the main structure, engineers will deliver permanent highway works, including the installation of lighting, drainage, kerbs and the final carriageway alignment. The fully completed bridge and permanent road layout are expected to be operational by summer 2028.
Image credit: HS2