HS2 1100 tonne viaduct

HS2 moves 1,100 tonne viaduct

HS2 has released timelapse and drone footage showing contractors moving a 1,100 tonne composite viaduct into place over two M42/M6 link roads in North Warwickshire.

The 158-metre-long structure was moved into place in just 13 hours using a specialist push-pull jacking technique.

The 'East M42-M6 Link Viaduct’ is one of 13 viaducts which make up HS2’s triangular Delta Junction. This section of the railway enables high speed trains to travel between London, Interchange Station in Solihull and Birmingham Curzon Street Station.

The operation was completed 10 hours ahead of schedule. A road closure was put in place, enabling the motorway link roads to be opened earlier than planned.

 

It was delivered by a team of 25 people from specialist steelwork company Victor Buyck Steel Construction (VBSC), working on behalf of HS2’s main works contractor Balfour Beatty VINCI (BBV).

HS2 Ltd, BBV and National Highways collaborated to minimise disruption for people using the roads and enabling this engineering feat to take place.

This was the second ‘launch’ of this structure to move it into its final position over both westbound and eastbound motorway link roads. In February, the first launch took the first 84 metre section of the viaduct to its halfway position over the westbound link road.

Since then, three further steel girders were welded to the back of the first section and 38 precast concrete slabs were installed to complete the 158-metre-long structure. By installing the slabs prior to launch, the number of highway closures required to finish the composite deck has been significantly reduced.

Over the summer, a similar two-stage operation will move the identical ‘West M42-M6 Link Viaduct’ which runs parallel to the East Link Viaduct.

Image Credit:  HS2

RTM

RTM April/May 24

INTELLIGENT WAYFINDING FOR A MORE INCLUSIVE RAILWAY

Immerse yourself with the latest thought leadership on intelligent wayfinding for a more inclusive railway, a revolutionary approach to investment in the south, and strategic investments unlocking the North’s potential.

More articles...

View all
TransCityRail Banner

TransCityRail

Mids \ 29 02 24
South \ 11 07 24
North \ 07 11 24

TransCityRail is a series of regional, interactive and insightful events across the country bringing together leaders, collaborators, problem solvers and innovators in a creative and invigorating way.
 

This series of events supports and informs the whole of the rail industry and connects suppliers with buyers, specifiers, leaders and decision-makers looking to procure a wide variety of innovative products and services for their region.

11/07/24

TransCityRail SOUTH

The South of England accounts for a significant portion of the UK’s rail investment strategy and is home to 7 sub-national transport bodies that have all placed rail infrastructure at the centre of their strategic investment plans.

Every year industry leaders from Network Rail, HS2, Train Operators, major contractors and transport bodies converge at the TransCityRail SOUTH conference, exhibition and networking dinner for a day of collaboration, conversation and engagement.

At this year's event, we're discussing...