Nuneham Viasuct piles waiting to be fitted

Network Rail continue emergency work to repair Nuneham viaduct in Oxfordshire

Emergency work on Nuneham Viaduct in Oxfordshire is progressing with Network Rail expecting work to be completed by June 10.

The bridge, located in Abingdon has been closed since early April so urgent works could be completed by Network Rail. Significant movements were located in the viaduct, with the south bank abutment, which was originally built in 1856 showing serious structural issues. The line between Didcot and Oxford was then shut to accommodate the works.

The abutment has now been completely removed with work now underway to install foundations for a completely new structure that will reinforce the viaduct.

The project has included some complex and challenging engineering, including:

  • 24 x 15m long steel piles have been driven into the bed of the River Thames to create a solid platform for the temporary structure that is currently holding the weight of the viaduct.
  • A 750-tonne crane was used to lift the temporary structure into place.
  • 3,000m3 of material has been removed from the embankment to create space to build a new abutment.

Operators including Great Western Railway, Chiltern Railways and CrossCountry have worked closely with Network Rail in order to keep trains moving whilst the section of line is being repaired.

Network Rail capital delivery director Stuart Calvert said: “The progress we have made on what is an extremely challenging project is testament to the diligence and talent of our teams.

“There is more hard work to come but we continue to operate round the clock to reopen the viaduct by 10 June.

“We apologise for the continued disruption for railway users but we are doing everything we can to get the railway running again as quickly as possible.”

“There is more hard work to come but we continue to operate round the clock to reopen the viaduct by 10th June.

“We apologise for the continued disruption for railway users but we are doing everything we can to get the railway running again as quickly as possible.”

Emergency work on Nuneham Viaduct in Oxfordshire is progressing with Network Rail expecting work to be completed by June 10.

The bridge, located in Abingdon has been closed since early April so urgent works could be completed by Network Rail. Significant movements were located in the viaduct, with the south bank abutment, which was originally built in 1856 showing serious structural issues. The line between Didcot and Oxford was then shut to accommodate the works.

The abutment has now been completely removed with work now underway to install foundations for a completely new structure that will reinforce the viaduct.

The project has included some complex and challenging engineering, including:

  • 24 x 15m long steel piles have been driven into the bed of the River Thames to create a solid platform for the temporary structure that is currently holding the weight of the viaduct.
  • A 750-tonne crane was used to lift the temporary structure into place.
  • 3,000m3 of material has been removed from the embankment to create space to build a new abutment.

Operators including Great Western Railway, Chiltern Railways and CrossCountry have worked closely with Network Rail in order to keep trains moving whilst the section of line is being repaired.

Network Rail capital delivery director Stuart Calvert said: “The progress we have made on what is an extremely challenging project is testament to the diligence and talent of our teams.

“There is more hard work to come but we continue to operate round the clock to reopen the viaduct by 10 June.

“We apologise for the continued disruption for railway users but we are doing everything we can to get the railway running again as quickly as possible.”

“There is more hard work to come but we continue to operate round the clock to reopen the viaduct by 10th June.

“We apologise for the continued disruption for railway users but we are doing everything we can to get the railway running again as quickly as possible.”

Want to know more about the opportunities to become a key supplier to the UK rail industry? Attend TransCityRail and access an exclusive marketplace of buyers from Network Rail, HS2, Train Operators, Major Contractors, and all other tiers of the supply chain. For more information and to secure your place click here.  

RTM OCTOBER/NOVEMBER 2023

RTM OCTOBER/NOVEMBER 2023

Putting Passengers First

This issue highlights the latest topics within the rail industry, from decarbonising the Midlands, improving rail safety, meeting the future priorities of Scotland's Railway & more!                                                      

Videos...

View all videos
TransCityRail Banner

TransCityRail

South \ 28 09 23
North \ 09 11 23
Mids \ 29 02 24

TransCityRail is a series of regional, interactive and insightful events across the country bringing together leaders, collaborators, problem solvers and innovators in a creative and invigorating way.
 

This series of events supports and informs the whole of the rail industry and connects suppliers with buyers, specifiers, leaders and decision-makers looking to procure a wide variety of innovative products and services for their region.

09/11/23

TransCityRail North

The North of England is home to almost a quarter of the UK’s entire population, so it’s no surprise that continued investment across the regions railway is a priority for Transport for the North, Network Rail, HS2, Operators and Major Contractors.

For over a decade the TransCityRail NORTH conference, exhibition and networking dinner has been uniting the leaders of industry responsible for building shaping and delivering rail infrastructure investment across the region for a day of collaboration, conversation and engagement.

This year we have another star studied line-up of keynote speakers and panel discussions on strategic rail investment for the region, Transpennine Route Upgrade and Northern Powerhouse Rail revealing £billions in opportunity for the supply chain.

More articles...

View all