HS2’s biggest tunnel site reaches milestone

HS2’s biggest tunnel site reaches milestone

HS2 has reached another significant milestone at the high-speed rail project’s first tunnel site, with the completion of structural work on the temporary pre-cast factory which will produce wall sections for the 10 mile stretch Chiltern tunnels.

The tunnel precast factory, and all 2,400 tonnes of structural steelwork at the south portal site, next to the M25, will be made in the UK and delivered by expert steel fabrications, Caunton Engineering, from their base near Moorgreen, Nottinghamshire.

The factory will permit HS2’s main works contractor, Align JV, a joint venture made up of three companies: Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick, to cast all sections of the tunnel on site meaning less HGVs on local roads.

The recently named giant tunnelling machine, Florence and Cecilia, are to come into action next year. The 170m long, 2,2000 tonne machines will spend more than 3 years underground and use 112,000 concrete segments to line the tunnels, moving at a speed of 15.6m a day.

A second precast plant will be used to cast sections for the nearby Colne Valley Viaduct. Once work is complete, the pre-cast plants will be taken apart and the whole site will be landscaped with material quarried from the tunnels and trees planted in order to blend it in with the surrounding countryside.

In addition to the precast plant, Caunton Engineering are also bringing structural steelwork for the general warehouse, workshops, soil treatment plant and the viaduct pre-cast plant. In total, around 2,400 tonnes of steelwork will be delivered from their factory in Moorgreen, Nottinghamshire, on the site of the former colliery.

HS2 Ltd’s C1 Senior Project Manager, Mark Clapp said: “The pre-cast plant will play a crucial role in delivering the Chiltern tunnels. By casting all 112,000 segments on site, we can significantly reduce the number of HGVs on local roads, reducing disruption for the local community.

“I’d like to thank everyone at Align and especially Caunton for their hard work in making it happen. Caunton’s involvement shows how HS2 is delivering for companies right across Britain, creating jobs and helping the economy recover from the pandemic.”

Daniel Altier, the Align Project Director, said: “Caunton Engineering is delivering the steel for all the structural buildings at our south portal site, 15 in total. This includes two tunnel pre-cast factories, the tunnel workshop and warehouse, and the viaduct precast factory. In selecting Caunton we opted for a company that can deliver a high-quality product and value for money. The selection of key suppliers such as Caunton is essential in order that we can deliver the project on time and on budget.”

Matthew Shimwell, Caunton’s Managing Director said: “We are thrilled to be working with the Align team in helping to deliver this key part of infrastructure work. The project is an excellent example of how early engagement with the supply chain brings real value to a project.

“This collaborative approach has helped to optimise the design of the buildings to more fully benefit from an informed DFMA approach (Design for Manufacture and Assembly). We wish the project team every success as it enters the next key stage in delivering this prestigious project.”

Image: HS2 

RTM OCT/NOV 21

RTM OCT/NOV 21

Delivering High Speed Two

Our October/November 2021 edition of RTM is packed with insights and visions for a future UK railway which is safe, efficient, and resilient. We delve into the restoration works at Bristol Temple Meads station with Maxine Prydderch, learn from Orlando De Leon about an innovative new piece of technology, and explore with HS2 Ltd’s Director of Stations & Systems, Chris Rayner, some of the successes already seen on HS2. That and so much more is available within the digital pages of our latest edition, so jump in and explore…

 

 

Videos...

View all videos
Regional Investment

RTM365 Online Festival

Regional Investment
9 December 21

The rail industry is undergoing a once-in-a-generation transformation with railways about to undergo the most significant transformation in 25 years.

We will be able to provide a more dependable and well-connected passenger first railway as a result of the network improvement. But what does this entail for individual locations in terms of investment?

On the 9th December, RTM365 will bring together leaders from each of the UK regions at our next instalment of virtual events to get the answer to these questions and learn more about regional rail investment, major projects and the effect of the upcoming Great British Rail transition.

Podcast

The Green Rail Revolution

Maria Machancoses, Director of Midlands Connect discusses the importance of HS2 to the Midlands and the UK, their collaborative work with the Department for Transport, and how we need to embrace the railways again.

More articles...

View all