Plans for the next major phase of Oxford station’s transformation are gathering pace, with Network Rail progressing proposals for a new through platform and western entrance designed to boost capacity and improve passenger access ahead of anticipated growth in rail demand.
Subject to funding approval and the award of a main construction contract, both elements are currently expected to open by summer 2029.
The scheme forms a key part of efforts to futureproof Oxford station, enabling it to accommodate increasing passenger numbers and support future rail developments, including East West Rail services, the proposed reopening of the Cowley Branch Line and wider growth across the city and surrounding region.
Design work on the western entrance has now resumed and is being refreshed to reflect updated passenger forecasts. These forecasts take into account expected demand generated by East West Rail and the planned Universal Resort development in Bedfordshire. The revised design is expected to progress through the planning process by mid-2027.
Current proposals for the western entrance include ticket machines, ticket gates and passenger toilets. Additional cycle parking, along with dedicated pick-up and drop-off facilities, are also under consideration.
Tom Pierpoint, industry programme director for Network Rail’s Great Western route, said:
“The new platform and western entrance are a really important part of preparing Oxford station for the future, giving passengers another way in and out of the station while creating the extra capacity needed to support more train services.
“We know delivering the next phase of the upgrade will have an impact locally, particularly around Roger Dudman Way. We’re looking carefully at how we can reduce that disruption and will keep residents and businesses informed as the plans develop.”

A significant element of the programme will involve construction activity around Roger Dudman Way. Under the current indicative timetable, the route would need to close to through traffic for approximately 20 months while major engineering works are undertaken.
Despite the closure, pedestrian and cycle access would remain available throughout, while diversion routes would be provided for vehicles requiring local access.
The works are required to facilitate the construction of new road and rail bridges at Sheepwash, alongside the diversion of utility infrastructure including pipes and cables. Plans also include a temporary footbridge and a road diversion to maintain local connectivity during construction.
Network Rail said it is continuing to work with contractors and project partners to minimise both the duration and impact of the closure. This could include undertaking some construction activities around the clock where appropriate.
Further details on piling works and other construction activity will be shared with local residents once the programme has been finalised.
Importantly for passengers and road users, Botley Road and its pedestrian walkways are expected to remain open throughout the remainder of the project.
Meanwhile, works associated with the previous phase of the Oxford station upgrade are nearing completion. These include finishing the temporary junction linking Cripley Road and Roger Dudman Way, replacing temporary railings with permanent installations and repairing paving in Frideswide Square. Construction of the new southern walkway along Botley Road is also continuing during overnight possessions to reduce disruption.
The planned western entrance and additional platform sit within a broader long-term vision for the station and surrounding area. Future proposals being explored include a new eastern entrance, a dedicated cycle hub, improved interchange with other transport modes, enhancements to public spaces and potential development around Beckett Street.
A public consultation on these wider plans is provisionally expected to take place between late May and early July 2027.
Image credit: Network Rail