NAO criticises DfT and NR failure to manage GWML electrification

The modernisation of the Great Western railway will need to be reassessed after recent setbacks to ensure that it still offers value for money, a National Audit Office (NAO) report has stated today, after the DfT revealed four deferrals to the project yesterday.

The cost of improving the route, which connects London with west and south-west England and south Wales, has increased by £2.1bn since 2013 and up to three-year delays to the electrification of the route will cost the DfT a further £330m.

The modernisation of the route, due to involve infrastructure works, new Intercity Express trains and service changes, aims to improve what is already one of the most overcrowded lines in England and Wales and is seen as necessary in order to accommodate forecast further passenger growth of 81% by 2018-19.   

Amyas Morse, head of the NAO, said: “The modernisation of the route has potential to deliver significant benefits for passengers but this is a case study in how not to manage a major programme.

“The department's failure to plan and manage all the projects which now make up the Great Western Route Modernisation industry programme in a sufficiently joined-up way, combined with weaknesses in Network Rail's management of the infrastructure programme, has led to additional costs for the taxpayer.”

The NAO criticised the DfT for not bringing together a business case outlining all elements of the programme until March 2015, more than two years after it initially ordered new trains. This led to Network Rail re-planning the infrastructure programme when it became clear that the initial schedule could not be met.

The report has also blamed Network Rail for its “unrealistic” cost estimate of the project in 2014, which overestimated the impact of new technology, and its failures in planning and delivering the infrastructure programme – such as a minimum feasible schedule for the work and sufficiently detailed site surveys. Electrification between Maidenhead and Cardiff is now expected to cost £1.2bn more than the 2014 cost estimate.

DfT now intends to vary its order of Intercity Express trains so that they can operate under both diesel and electric power. However, the NAO has cautioned that the budget and schedule for electrification may still be over-optimistic, as the DfT will receive less money from the Great Western franchise prior to 2019 while the operator bears the costs of the delays.

“It is encouraging that since 2015 the department and Network Rail have a better grip and put in place structures to manage the programme in an integrated way,” Morse said. “However, significant challenges to the timetable still remain and there is more to do to achieve value for money.”

Due to budget constraints and delays, it is now envisaged that Great Western passengers in the north and west of England will have to wait for up to two years to start seeing benefits. Some stretches of the route will also not be electrified until the next rail investment period, which runs from April 2019 to March 2024.

Mick Whelan, general secretary of Aslef, the train drivers’ union, said: “The decision to defer the electrification of the line between Oxford and Didcot Parkway; of Filton Bank (Bristol Parkway to Bristol Temple Meads); west of Thingley Junction (Bath Spa to Bristol Temple Meads); and the Thames Valley branches (Henley & Windsor) is another blow to Britain’s railway industry and another example of the DfT’s incompetence.”

(Image: FGW GWR class 43 c. Nick Rice, Flickr)

Have you got a story to tell? Would you like to become an RTM columnist? If so, click here.

Comments

Huguenot   11/11/2016 at 15:23

"it is now envisaged that Great Western passengers in the north [and west] of England will have to wait for up to two years to start seeing benefits." Is this a new push by GW north of Birmingham? They did reach Birkenhead and Warrington, of course, but never Manchester, Leeds. Seriously, though, here are some of the obvious cost overruns in this farce: * over-engineered OHLE. * High Output Plant System too inflexible and not fit for purpose. * failure to record trackside cablling, leading to damage by excavations. * unnecessarily extravagant clearances for overhead wiring. * failure to seek derogations for bridge parapet heights. * unwise decision not to work outwards from London and electrify suburban services first (as was done with MML and ECML) and so reap suburban benefits early on. * premature ordering of IEPs (DfT's fault, not NR's).

Roger Capel, Sheffield & Glossop   14/11/2016 at 12:49

Huguenot, there is GWR electrification from Chester to Birkenhead, only it's DC 3rd rail. Not much hope of extension there then-------. Seriously though, your last point goes a lot deeper. Never EVER AGAIN should any sane person order a fleet of rolling stock & then expect to fit a major electrification round it. I've lost count of the people who've said that IEP should have been "ECML First", with somewhere ready to operate it & iron out the wrinkles. As for the over-engineered OHLE, I'm a regular traveller on the stub of the Manchester - Sheffield - Wath, with its fairly bomb proof LNER/BICC ex-1500v overhead line (see also GE Suburban, but without the compound catenary). What's going up on the GWML makes the MSW look like Meccanno. What was BR telling us in the 60s about 25Kv being lighter & cheaper? One of their engineers proudly told the press that their arch structure cross beams can move up & down, as though that was new. May I direct anyone who thinks it is to Structure MH11-22, at the west end of Dinting viaduct. It's a 70 year old design & it's called a subsidence structure, mate.

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

13/06/2019Dawlish railway may be ‘moved out to sea’ to protect it from storms under new proposals

The storm-battered Dawlish rail line could be “moved out to sea” and away from the “hazard” of the cliffs under new plans... more >
TfL awards contract for new DLR fleet to replace 30-year-old trains

12/06/2019TfL awards contract for new DLR fleet to replace 30-year-old trains

TfL has awarded a contract for 43 new trains to replace the oldest rolling stock on the Docklands Light Railway (DLR), with the first scheduled t... more >
Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projec... more >
Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey&rsqu... more >
read more blog posts from 'the sleeper' >

comment

Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >
Malcolm Holmes on new stations for the Black Country

10/06/2019Malcolm Holmes on new stations for the Black Country

Malcolm Holmes, executive director of the West Midlands Rail Executive, described the new stations set to be built for the Black Country region o... more >
The skills bottleneck: Dealing with growing apprenticeship demand

10/06/2019The skills bottleneck: Dealing with growing apprenticeship demand

Richard Turner, head of apprenticeships at Network Rail, details the reasons for growing apprenticeship demand in the rail sector over the coming... more >
A train journey on the Midland Main Line 15 years from now…

10/06/2019A train journey on the Midland Main Line 15 years from now…

Chris Hobson, director of policy and external affairs at the East Midlands Chamber, talks in detail about what travelling through the region will... more >