ORR to grill Network Rail over CP5 missed targets

The Office of Rail and Road (ORR) is investigating Network Rail’s performance and its capability to deliver the massive CP5 enhancements programme, having missed 30 of its 84 milestones for 2014-15 and with many projects facing delays and rising costs

Renewals are also significantly behind schedule, especially overhead line (77% behind) and signalling (63% behind). Track renewals are 7% behind plan. 

Signalling renewals behind

The ORR recently launched a formal investigation into Network Rail’s enhancement delivery, and another into train performance, specifically for Southern and Govia Thameslink Railway, as well as Scotland. 

Network Rail is responsible for delivering more than £12bn of enhancements to the rail network such as new stations, electrification and bridges by 2019. Of the 30 missed milestones (full list at the bottom of the article), 16 of these were development milestones – meaning the scheme design is running behind plan. The remaining 14 were project completion milestones. Although many of these did not significantly impact Network Rail’s customers, ORR said there were notable occasions where the introduction of new and improved services was delayed.

The most prominent example was phase 2b of the North West Electrification project (Liverpool-Manchester, including Liverpool-Wigan) which missed the December 2014 completion date for the introduction of electric services. The infrastructure was not ready for authorisation until March 2015. 

Other missed milestones, such as Swindon resignalling and Reading to Didcot electrification, were communicated at short notice, the ORR added. 

The regulator said: “We reported in the last monitor that we have formerly escalated several concerns related to enhancement projects and Network Rail’s ability to deliver its regulated obligations. These concerns can be summarised as follows:

  • shortcomings in project design and development, including inadequate rigour in cost estimating;
  • late project delivery;
  • shortcomings in how Network Rail delivers its part in cross-industry programmes such as Great Western Route Modernisation; and
  • lack of evidence that Network Rail is managing the CP5 investment portfolio to achieve efficiencies.” 

Performance on the East Coast Main Line and freight sector has been good, however, overall punctuality of train service performance remains at 89.6% – 2.9 percentage points lower than the 92.5% target. 

269 PPM resize 635697008657483447

The latest six-monthly ORR Monitor shows declining operator satisfaction with Network Rail:

TOC satisfaction with NR

The Monitor notes: "For the first time since the survey was introduced the number of 'dissatisfied' or 'very dissatisfied' customers was greater than those satisfied (41%). This is a striking result given that satisfaction with train performance in fact increased by 4% compared with 2013."

Another problem is poor drainage. The ORR says: "There were many earthworks failures during the wet weather over the winter of 2013-14 and these were partly attributable to historic problems with drainage. We are still not satisfied that Network Rail is doing enough in this area and we issued an improvement notice on the 18 February 2015 covering the management of critical drainage system components."

However, one bright spot is the ORBIS project to vastly improve asset information quality and functionality. The Monitor says: "To date all milestones have been achieved on schedule, including for the signalling core data, which was completed in January."

ORR chief executive Richard Price said: “Network Rail has made a slow start in delivering on its enhancements and performance targets for CP5 and we have asked it to demonstrate how it plans to get back on schedule to deliver on its commitments to 2019. 

“ORR is investigating Network Rail’s performance improvement plans and delivery of enhancements. This work will help identify the issues the company needs to address to improve train performance, increase capacity and deliver on its commitments to passengers.” 

Patrick Butcher, finance director at Network Rail, said that while progress is being made in improving performance, safety, asset reliability and delivering more renewals and projects, “our rate of acceleration in these areas isn’t yet where we want it to be”. 

“With more than a million more trains on the network than 10 years ago, there are inevitable challenges,” he said. “We are determined to do more to improve and action is being taken to quicken the pace of change.” 

David Sidebottom, passenger director at the independent watchdog Transport Focus (formerly Passenger Focus), said passengers tell his organisation that punctual trains are their main priority. 

“Passengers welcomed news that there would be investment in schemes to deliver on their priority areas for improvement,” he noted. “It is disappointing that these are behind schedule. It is now vital that Network Rail is even more focused on delivering a good passenger experience through times of disruption due to these works.” 

Transport secretary Patrick McLoughlin MP said: “I expect the regulator to hold Network Rail to account, performance must and should improve. The industry has to work together to address these failings and deliver for passengers and the economy: that needs to start now.” 

Following ORR’s investigation into project over-runs at Christmas, Network Rail has implemented new plans and recommendations for engineering works to minimise impact on passengers in time for engineering works planned over Christmas 2015. 

Missed Project Completion Milestones (GRIP 6 milestones) 

  • Package 7, 10 Car South West Suburban Railway - Reynes Park to Dorking
  • Motherwell Area Stabling - Phase 1
  • Barry - Cardiff Queen Street Corridor - Phase 2 - Valley Lines
  • Barry - Cardiff Queen Street Corridor - Phase 3 - Barry Lines
  • Strategic Freight Network (SFN) - Ipswich Yard
  • Chiltern Main Line Lengthening - Except High Wycombe DOWN platform
  • Rolling Programme of Electrification - Rutherglen and Coatbridge (R&C) Electrification
  • Barry - Cardiff Queen Street Corridor - Phase 4 - Cardiff East
  • Strategic Freight Network (SFN) - Peak Forest
  • North of England Programmes (LNW) - Phase 2 (c) - (NW Electrification Phase 2 Configuration State 3)
  • Belcombe to Copyhold Bi-directional Signalling Upgrade
  • North of England Programmes (LNW) - Phase 2 (a&b) - (NW Electrification Phase 2 Configuration State 3)
  • St Pancras - Sheffield Linespeed Improvements
  • Stations - Access for All (AfA) - New Cross Gate

 Missed Project Development Milestones (GRIP 3 milestones) 

  • Great Western Electrification - Maidenhead to Newbury, Oxford, Chippenham and Bristol Parkway
  • Great Western Electrification - Chippenham to Bristol Temple Meads
  • North of England Programmes (LNW) - Phase 4 - Manchester to Preston Electrification and Preston JTI - (NW Electrification Phase 4 - Configuration State 5)
  • Intercity Express Programme: Western Capability - Route wide (gauge capacity works all routes)
  • Oxford Corridor Capacity Improvements - Phase 1
  • London Victoria Station Capacity Improvements
  • Great Western Electrification - Bristol Temple Meads and Bristol Parkway to Cardiff
  • Acton (GWML) to Wilesden (WCML) Electrification (Acton West to Acton Wells)
  • Anglia Traction Power Supply Upgrade - GE bulk supply point & AT
  • Ely North Junction Capacity Improvement
  • North of England Programmes (LNW) - Phase 3 - Preston to Blackpool Electrification - (NW Electrification Phase 3 - Configuration State 5)
  • North of England Programmes (LNW) - Phase 5 - Guide Bridge to Stalybridge Jcn Electrification - (NW Electrification Phase 5 TPE West - Configuration State 7)
  • North of England Programmes (LNW) - Phase 5 - Manchester Victoria to Stalybridge Jcn Electrification and JTI - NW Electrification Phase 5 TPE West - Configuration State 5)
  • Northern Programme (Yorkshire) - Calder Valley
  • Oxford Corridor Capacity Improvements - Phase 1
  • Sussex Power Supply Upgrade

Tell us what you think – have your say below or email opinion@railtechnologymagazine.com

Comments

There are no comments. Why not be the first?

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Regional leaders call for HS2 to be completed all the way

21/06/2019Regional leaders call for HS2 to be completed all the way

HS2 must be completed all the way to the North and integrated with Northern Powerhouse Rail to achieve the maximum impact on rebalancing the UK&r... more >
Leading Women in Rail campaigner Anna Delvecchio honoured with portrait plaque at London Transport Museum

20/06/2019Leading Women in Rail campaigner Anna Delvecchio honoured with portrait plaque at London Transport Museum

Anna Delvecchio, the Rail Sector Deal co-lead and Amey’s commercial account director, has received unique recognition from the Rail Supply ... more >
Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

20/06/2019Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

RTM talks exclusively to one of the rising stars of the industry and Transport’s Woman of the Year 2018, Anna Delvecchio. Amey’s... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projec... more >
Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey&rsqu... more >
read more blog posts from 'the sleeper' >

comment

Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

20/06/2019Challenging perceptions of apprenticeships in the rail industry with Anna Delvecchio

RTM talks exclusively to one of the rising stars of the industry and Transport’s Woman of the Year 2018, Anna Delvecchio. Amey’s... more >
Hitachi trains for Happy trains

10/06/2019Hitachi trains for Happy trains

ScotRail project manager Kirsty Devlin discusses the withdrawal of Class 365s, to be replaced with the brand-new Class 385 fleet. While Scot... more >
Malcolm Holmes on new stations for the Black Country

10/06/2019Malcolm Holmes on new stations for the Black Country

Malcolm Holmes, executive director of the West Midlands Rail Executive, described the new stations set to be built for the Black Country region o... more >
The skills bottleneck: Dealing with growing apprenticeship demand

10/06/2019The skills bottleneck: Dealing with growing apprenticeship demand

Richard Turner, head of apprenticeships at Network Rail, details the reasons for growing apprenticeship demand in the rail sector over the coming... more >