Farnworth Tunnel electrification work to start next week

Farnworth Tunnel closes for six months from next week as Network Rail rebuild it as part of the Manchester to Preston electrification project.

The closure of one of the two tunnels for rebuilding between Saturday 2 May and Sunday 4 October will cause major disruption to services between Bolton and Manchester, with an amended timetable in action.

The other tunnel will remain open, to allow some train services to continue to operate.

The existing tunnels are too small for the overhead lines needed so one of them is being filled in with concrete and then re-bored, making it large enough for both sets of railway lines and the overhead equipment.

Network Rail will also be reconstructing a retaining wall, reconstructing a road bridge, making changes to both platforms at Farnworth Station, installing new track between Bolton and Moses Gate, making alterations at Moses Gate Station and replacing a pedestrian level crossing near Kearsley with a footbridge.

Around 7,000 people travel on the route between Preston and Manchester in peak times with around 2,000 joining at Bolton. Passengers are being asked to avoid travelling through Bolton and travel via Preston and Wigan if possible.

A spokesperson on behalf of Northern Rail and First TransPennine Express commented: “The work will lay the foundations for a much improved railway, where in the future we are able to provide more capacity, faster journeys and a greener travel experience.

“However this engineering project is extremely complex and we appreciate the disruption that it will cause to customers’ journeys.”

As well as the amended weekday service, there will be no trains running between Bolton and Manchester during weekends until the railway reopens on Monday 5 October.

Tell us what you think – have your say below or email [email protected]

Comments

Kevin Bennett   08/05/2015 at 20:56

Seems like a good option - for tunnelling contractors! How about a method that cuts strengthening ribs into the roof of the tunnel, that then allows the crown to be ground back until sufficient clearance is achieved? And futher, do one rib per night (cut and replace) so the tunnel can still be used during the day. Interested? Call Freyssinet 07788 658721. Its been done before many times.

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >
GTR spreads messages of support on Suicide Prevention Day

10/09/2020GTR spreads messages of support on Suicide Prevention Day

As today (10 Sept) mark the annual World Suicide Prevention Day, Govia Thameslink Railway (GTR), have revealed ‘Affirmation Art’ clus... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News