Progress on Birmingham HS2 Viaduct continues

Progress on Birmingham HS2 Viaduct continues

Construction is progressing well on the 300 metre-long viaduct that will bring high-speed trains into Birmingham's Curzon Street Station.

Over 2,000 cubic metres of concrete have been poured to create the first two 90 metre viaduct deck structures, with construction of two further deck sections well advanced.

The concrete was delivered and poured during night-time operations to minimise impacts on local roads. In total over 11,000 cubic metres of concrete will need to be poured to complete the whole viaduct.

A total of 26 piers, between five and six metres tall, have also been built to carry the viaduct, with 4 huge steel tripods currently under construction to support the viaduct over Digbeth Canal.

Over the next few months, once the concrete has been poured on each section, the shuttering and scaffolding will be removed, the viaduct sections will receive precast parapets and other finishing works will start.

Further sections of the viaduct will be built in the same way, and next summer, the span over the canal will be completed using jacks to slide 34 temporary steel girders, each measuring 38 metres, below the four steel tripods to support the formwork and further deck construction.

Curzon Viaduct No.3 is part of a series of five connected viaducts between Washwood Heath and Curzon Street Station in central Birmingham. On the approach to the station, the viaduct widens from a single deck to four separate decks, spanning 65 metres at the wideset point, to carry seven tracks to the platforms. Work on Curzon Street Station will begin next year.

David King, Senior Project Manager at HS2 Ltd said: “It’s fantastic to see this iconic viaduct taking shape in central Birmingham. This is one of our busiest construction sites, as we now reach peak construction on key HS2 structures across the Midlands, with over 9,750 people in the region working on the project.”

“The design of the viaduct is part of our vision to maximise social and economic development opportunities around Curzon Street Station. Widening to four separate decks near the station will maximise daylight underneath the viaduct, creating opportunities for a usable and flexible public space.”

Lenka Vosvrdova, Curzon Street site agent at Balfour Beatty VINCI added: “We’re extremely proud of the significant progress our team have made on the Curzon Street Viaduct site. Since we revealed the first giant pier in January this year, we have successfully constructed 26 new concrete piers, with the first sections of the four-span viaduct also nearing completion.

“Over the coming months, works will ramp up on the series of viaducts in Birmingham, as we continue to build structures over Digbeth Canal, Lawley Middleway and the original Victorian railway line.”

Photo: HS2

RTM

RTM Feb/Mar 24

Rail station: Metamorphosis

This issue highlights the latest topics within the rail industry, from new West Midlands railway stations to decarbonisation Govia Thameslink Railway.

More articles...

View all
TransCityRail Banner

TransCityRail

Mids \ 29 02 24
South \ 11 07 24
North \ 07 11 24

TransCityRail is a series of regional, interactive and insightful events across the country bringing together leaders, collaborators, problem solvers and innovators in a creative and invigorating way.
 

This series of events supports and informs the whole of the rail industry and connects suppliers with buyers, specifiers, leaders and decision-makers looking to procure a wide variety of innovative products and services for their region.

11/07/24

TransCityRail SOUTH

The South of England accounts for a significant portion of the UK’s rail investment strategy and is home to 7 sub-national transport bodies that have all placed rail infrastructure at the centre of their strategic investment plans.

Every year industry leaders from Network Rail, HS2, Train Operators, major contractors and transport bodies converge at the TransCityRail SOUTH conference, exhibition and networking dinner for a day of collaboration, conversation and engagement.

At this year's event, we're discussing...