Croxley rail link secures final funding and is renamed Metropolitan Line Extension

TfL has confirmed that construction work is to start on the delayed Croxley rail link next year, meaning that a funding gap of £2.73m has now been closed. 

A full funding package for the Metropolitan Line Extension has been agreed between the Department for Transport (DfT), Hertfordshire County Council (HCC) and TfL, and the work will now be delivered by London Underground. 

The link, which will extend the Metropolitan Line to Watford Junction via Watford High Street, was originally meant to be complete by May 2016, but will now be complete in 2020. 

Prior to the decision to go ahead with the work, whose costs have ballooned compared to initial estimates, RTM reported that TfL had to find £2.73m of unbudgeted funding after HCC tried paying part of its share with wasteland valued at £1

Nick Brown, managing director of LU, said: “For 100 years, the Tube has been enabling growth in ‘Metro-land’ and this new part of the Underground network will support further rapid development in the area. 

“By 2020 we will have built a 400m viaduct, two completely new stations and numerous new and reconstructed bridges along the route, transforming transport links in Watford. With the funding package complete we’re now turning all our attention to appointing contractors, finalising designs and beginning construction in 2016.” 

Hertfordshire Local Enterprise Partnership has committed £87.85m to the new Tube link, which is 40% of its total Growth Deal funding from government. Its chair, John Gourd, said: “The Metropolitan Line Extension will unlock investment in brownfield sites, revitalise existing employment areas and bring considerable job opportunities and economic benefits to Watford and the wider community.” 

It is expected that more than 6,500 permanent jobs and a £2bn boost to the local economy will be created as two new stations are built at Cassiobridge and Watford Vicarage Road.

Comments

Del   06/05/2016 at 22:16

So looking forward to seeing this overdue project brought to completion and then riding rails in person.

Add your comment

 

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

Apprentice to Co-leading the Rail Sector Deal

05/06/2019Apprentice to Co-leading the Rail Sector Deal

In a series of Q&A’s with key speakers on the run up to TransCityRail Midlands, we caught up with TransCityRail panellist and Amey’s commercial account director, Anna Delvecchio, for her insight into what the Rail Sector Deal mea... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

By Ewan Quayle, Rail Technology Magazine Reporter Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that ... more >
Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

24/06/2019Malcolm Holmes, executive director of West Midlands Rail Executive, announced as TCR Midlands speaker in Birmingham

Ahead of his appearance, Malcolm Holmes spoke with Rail Technology Magazine about what key leaders in the industry were doing to improve rail in the Midlands. He said: “It’s very... more >