Network Rail ‘breaching contract’ with Virgin

Virgin Rail is accusing Network Rail of having “consistently failed to deliver what it is contracted to deliver” and says its level of poor performance could amount to breach of contract.

The operator wants any penalties imposed by ORR for poor performance to be made up by Network Rail in the form of improvements for passengers, not fines that go straight to the Treasury.

Problems with infrastructure on the West Coast Main Line have deterred some passengers from travelling, Virgin Rail said, damaging its business. Network Rail has missed targets agreed with Virgin over the last two years, with the latest punctuality figures at 85.7%, short of the 88% target.

Over 70% of delays are a result of infrastructure issues, Virgin stated, with fewer than 15% of delays being the operator’s fault.

Tony Collins, chief executive officer of Virgin Rail, said: “Network Rail has consistently failed to deliver what it is contracted to deliver. That has directly affected customers’ experience, and their impression of rail travel. So any penalties levied on Network Rail should be in the form of tangible improvements that customers benefit from. There is really no benefit to Network Rail, customers or Virgin Rail Group in having money leave the industry.

“Providing world class customer service is the vision of Virgin Trains. We have spent hundreds of millions of pounds on a fleet of reliable trains and we pay Network Rail nearly £200m a year to maintain the West Coast Mainline for us.

“We feel that we are not getting value for money in this respect and our customers have been let down and deserve more consistency. We have made our case strongly over many years to Network Rail, ORR and Government. But reluctantly we have taken this difficult decision on behalf of our customers.”

Network Rail said it is working closely with Virgin to fix infrastructure problems on the WCML. Virgin’s chief operating officer Chris Gibb was seconded to Network Rail for five months last year to work on these issues.

Tell us what you think – have your say below, or email us directly at [email protected]

Comments

There are no comments. Why not be the first?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

Major station improvements and electric vehicle charging hubs

09/09/2020Major station improvements and electric vehicle charging hubs

Following the announcement of Govia Thameslink Railway’s (GTR) programme to develop numerous stations, today (9 Se... more >
Contract awarded by Network Rail to strengthen bridges

09/09/2020Contract awarded by Network Rail to strengthen bridges

Three contracts have been awarded by Network Rail to carry out strengthening work to three railway bridges across the We... more >
New electric train fleet revealed for Birmingham’s Cross-City Line

09/09/2020New electric train fleet revealed for Birmingham’s Cross-City Line

The electric train fleet set to transform travel on Birmingham’s Cross-City Line has been revealed to rail passeng... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme. Recognising that young people are more likely to take a risk trespassing on railway tracks, C... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >