Latest Rail News

15.02.16

Open access TOCs see steep falls in performance during period 11

The non-franchised sector saw a sharp decline in performance last month, with Grand Central and First Hull Trains PPM figures dropping by eight and 12 percentage points respectively compared to last year – despite both topping the recent National Rail Passenger Survey.

The Network Rail data, which covers operator performance for 10 January to 6 February (period 11), showed sharp deterioration across the two TOCs, with Heathrow Express being the only open access operator with an improved performance.

First Hull Trains saw the largest drop of all operators, with its PPM standing at 81.5% compared to 93.5% during last year’s period 11. Its delay and cancellation figure was also the highest of all operators, standing at 6.5%.

The operator also reported a particularly bad month during period 10, with a performance figure of 76.4% - significantly below the 85.9% recorded in the previous year. Almost 14% of its services at the time had also been delayed or disrupted.

Grand Central followed closely, with a PPM of 83.1% compared to 90.8% last year. Its delay and cancellation figure, however, stood unchanged at 4.3%.

A Grand Central spokesperson told RTM: "A number of temporary speed restrictions affected  PPM in the period.  We continue to work with Network Rail to ensure sustained improvement."

While these figures didn’t represent the worst performance data across the entire sector, they were amongst the sharpest falls within just one year. It also harshly contrasted with the high levels of passenger satisfaction recorded by both operators in the latest Passenger Survey, with First Hull actually topping that list – the largest of its kind in the world – at a rate of 97%.

560 ppm

Only two other operators, Virgin Trains East Coast and Southeastern, experienced comparable drops in performance in this latest period. The former saw a drop of 9.6 percentage points since last year to 91.7% now, and the latter a drop of 8.1 percentage points to 83.2%.

Virgin Trains East Coast – which took over the east coast route in March last year and, just today, introduced 42 new services between Edinburgh and London – also saw a rise in delays and cancellations during this period, with nearly 6% of its services either late by over half an hour or cancelled entirely.

Its sister franchise, Virgin Trains West Coast, saw an opposite pattern, with its delay figure dropping from 7.9% to 2.2%, and its PPM rising from 78.8% to 88.7%.

But despite their poor performance, the reasons behind delays and faults across Virgin Trains East Coast, Southeastern and Grand Central services were more accountable to Network Rail. In Virgin Trains’ case, for example, 77% of faults and delays of three minutes were attributable to Network Rail, compared to the national average of 59%.

Overall, the national PPM figure was of 88.4%, just very marginally above last year’s figure of 88%.

(Top image c. mattbuck)

Comments

Scottie   16/02/2016 at 16:04

Comment. Where are the stats for the Southern Railway Franchise on the above table ? Have they been included in the Govia Thameslink figures ? If this is the case surely a guidance note would be helpful ! I know the Travelling public in the UK must be patient, Must we now have the ability to be psychic as well ?

RTM   16/02/2016 at 16:10

Hi Scottie, Network Rail groups Southern under Govia because the franchise was absorbed in July. If you would like sub-operator figures, you can find them here: http://www.networkrail.co.uk/performance/sub-operator-PPM-figures.pdf

Andrew G   17/02/2016 at 23:33

In fairness. Abellio Greater Anglia are not improving their services as much at the moment with so many delays and cancellations which is such a headache. To be fair c2c are also not improving their services since they changed their timetables which has angered a lot of passengers since c2c changed the timetables back in December last year.

Add your comment

related

Rail industry Focus

View all News

Comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >

'the sleepers' blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s... more >
read more blog posts from 'the sleeper' >

Interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he would not rule out his organisation issuing future r... more >
Advancing the rail industry with management degree apprenticeships

08/05/2019Advancing the rail industry with management degree apprenticeships

In answering the pressing questions of how current and future generations of managers can provide solutions to high-profile infrastructure projects across the UK, Pearson Business School, part of... more >