03.11.14

Completion of Manchester to Liverpool electrification delayed

Network Rail will not complete the Manchester to Liverpool electrification project in time for the planned December launch of services, leaving bosses at Northern Rail “deeply disappointed”.

Northern had planned to start running two Class 319s on the line after the December timetable change, with a gradual roll-out of a further 12 over the next year. However this will now be pushed back into the new year, possibly as late as the end of February.

The delay has been blamed on “unexpected ground conditions and technical issues with the wiring equipment”, encountered while installing overhead catenary wires on the 184-year-old former Liverpool and Manchester Railway mainline.

Jim Syddall, route managing director for Network Rail, said: “We are making every effort to ensure the work is completed as soon as possible. We expect it to be completed by early 2015 and we will keep people informed as the work progresses. The rest of the north west electrification programme is not affected by this delay.”

The £400m programme includes the £160m upgrade of the line between Manchester and Liverpool and will cut journey time to just 30 minutes.

It is a key enabler for a planned doubling of service frequencies.

Alex Hynes, Northern Rail managing director, said: “We are deeply disappointed that work by Network Rail to electrify the Liverpool – Manchester line will not be completed to enable electric trains to be introduced from the December timetable change, as originally planned. However, we remain committed to working with them to ensure customers on the route will benefit from the additional capacity and more reliable journeys that electric trains will deliver as soon as possible.”

The first two Class 319s cascaded north from Thameslink arrived at the Allerton depot for driver training in September.

Northern said refurbishment work is being carried out at Wolverton by Knorr-Bremse under a Porterbrook contract, and Northern has also contracted Interfleet to undertake additional modifications. Refresh work on the trains includes: an exterior and interior repaint; refurbishment of seating; and fitting of door controls through all vehicles to allow conductor door operation from anywhere within the train.

Northern is reported to have told the Transport for Greater Manchester Rail & Metrolink Committee that the 319s will also get a new passenger information system and LED lighting. Four units were to be ready for December 2014; two in passenger traffic and two for maintenance spare and training.

In an interview with RTM in the summer, Network Rail’s principal sponsor for north west England, Martin Jurkowski, made clear how much work had to be done.

He said it was a “critical date”, just as the December 2013 first-phase electrification commissioning was, Manchester to the West Coast Main Line and Newton-le-Willows. That phase allowed First TransPennine Express to start running its electric services from Manchester Airport to Scotland.

Jurkowski told us then: “This December, the same is happening for Northern, with the introduction of electrified services between Liverpool and Manchester. There’s a lot going on collectively between us – driver training, depot electrification, and so on – for that to happen.”

Timeline

The original timeline for north west electrification was as follows:

Phase 1: Between Castlefield Junction and Newton Le Willows by December 2013

Phase 2a: Between Liverpool and Newton Le Willows

Phase 2b: Between Huyton and Wigan

Phase 2c: Between Ordsall Lane and Manchester Victoria, all by December 2014

Phase 3: Preston to Blackpool, by May 2016

Phase 4: Manchester Victoria to Preston (Euxton Junction), by December 2016

Phase 5: Manchester Victoria to Stalybridge, Guide Bridge to Stalybridge, December 2016

Tell us what you think – have your say below or email opinion@railtechnologymagazine.com

Comments

Pedr Jarvis   08/11/2014 at 19:13

Where were the unexpected ground conditions, please? Couldn't be Chat Moss, could it?

RTM   10/11/2014 at 08:36

We're still trying to get to the bottom of that one Pedr! (Let's hope not though...)

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

19/11/2018Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

Errors made during the derailment of a London Waterloo train last year showed lessons learned from the 1988 Clapham Junction disaster were &ldquo... more >
Wales and Borders rail to receive £2bn government funding

19/11/2018Wales and Borders rail to receive £2bn government funding

Network Rail Wales and Borders has announced £2bn in government funding to be spent on a project to maintain and renew the Wales and Border... more >
HS2 kicks off the bid race to build Curzon Street station

19/11/2018HS2 kicks off the bid race to build Curzon Street station

HS2 has announced the start of its search for contractors to build its new £435m Curzon Street station. Around four contractors will b... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Finding positives in negative short-circuiting devices

09/11/2018Finding positives in negative short-circuiting devices

Sponsored interview  Anything that brings about safety and time-saving benefits is a valued improvement for the rail industry, which is w... more >
Taking to the skies

30/10/2018Taking to the skies

Network Rail’s commitment to driving innovation is best encapsulated by its latest scheme involving high-definition imagery drones, or UAVs... more >
Going global: an interview with Network Rail’s Leevan Finney

29/08/2018Going global: an interview with Network Rail’s Leevan Finney

RTM’s Jack Donnelly sat down with one of the leading minds behind Network Rail’s most advanced and innovative rail maintenance techno... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

Elizabeth Line: short-term pain for long-term gain?

13/11/2018Elizabeth Line: short-term pain for long-term gain?

Tim Bellenger, director of policy and investigation at London TravelWatch, discusses the deferred opening of the central section of the Elizabeth... more >
read more blog posts from 'the sleeper' >

comment

Challenging the perceptions of rail

13/11/2018Challenging the perceptions of rail

Darren Caplan, chief executive of the Rail Industry Association (RIA) explains how the RIA Rail Fellowship Programme is challenging people’... more >
Data-driven rail

13/11/2018Data-driven rail

Andy Cross, director of Elastacloud, and Lucy Bealing, from the Elastacloud Rail Centre of Excellence, discuss their innovative collaboration wit... more >
Looking ahead to the Williams Review

13/11/2018Looking ahead to the Williams Review

Darren Shirley, chief executive of the Campaign for Better Transport, takes a look at the government’s root and branch review of the rail s... more >
Digital Railway: All change on the ECML

06/11/2018Digital Railway: All change on the ECML

Network Rail route programme director, Toufic Machnouk, explains why only a radically new approach to contracting will deliver a better service f... more >