Completion of Manchester to Liverpool electrification delayed

Network Rail will not complete the Manchester to Liverpool electrification project in time for the planned December launch of services, leaving bosses at Northern Rail “deeply disappointed”.

Northern had planned to start running two Class 319s on the line after the December timetable change, with a gradual roll-out of a further 12 over the next year. However this will now be pushed back into the new year, possibly as late as the end of February.

The delay has been blamed on “unexpected ground conditions and technical issues with the wiring equipment”, encountered while installing overhead catenary wires on the 184-year-old former Liverpool and Manchester Railway mainline.

Jim Syddall, route managing director for Network Rail, said: “We are making every effort to ensure the work is completed as soon as possible. We expect it to be completed by early 2015 and we will keep people informed as the work progresses. The rest of the north west electrification programme is not affected by this delay.”

The £400m programme includes the £160m upgrade of the line between Manchester and Liverpool and will cut journey time to just 30 minutes.

It is a key enabler for a planned doubling of service frequencies.

Alex Hynes, Northern Rail managing director, said: “We are deeply disappointed that work by Network Rail to electrify the Liverpool – Manchester line will not be completed to enable electric trains to be introduced from the December timetable change, as originally planned. However, we remain committed to working with them to ensure customers on the route will benefit from the additional capacity and more reliable journeys that electric trains will deliver as soon as possible.”

The first two Class 319s cascaded north from Thameslink arrived at the Allerton depot for driver training in September.

Northern said refurbishment work is being carried out at Wolverton by Knorr-Bremse under a Porterbrook contract, and Northern has also contracted Interfleet to undertake additional modifications. Refresh work on the trains includes: an exterior and interior repaint; refurbishment of seating; and fitting of door controls through all vehicles to allow conductor door operation from anywhere within the train.

Northern is reported to have told the Transport for Greater Manchester Rail & Metrolink Committee that the 319s will also get a new passenger information system and LED lighting. Four units were to be ready for December 2014; two in passenger traffic and two for maintenance spare and training.

In an interview with RTM in the summer, Network Rail’s principal sponsor for north west England, Martin Jurkowski, made clear how much work had to be done.

He said it was a “critical date”, just as the December 2013 first-phase electrification commissioning was, Manchester to the West Coast Main Line and Newton-le-Willows. That phase allowed First TransPennine Express to start running its electric services from Manchester Airport to Scotland.

Jurkowski told us then: “This December, the same is happening for Northern, with the introduction of electrified services between Liverpool and Manchester. There’s a lot going on collectively between us – driver training, depot electrification, and so on – for that to happen.”

Timeline

The original timeline for north west electrification was as follows:

Phase 1: Between Castlefield Junction and Newton Le Willows by December 2013

Phase 2a: Between Liverpool and Newton Le Willows

Phase 2b: Between Huyton and Wigan

Phase 2c: Between Ordsall Lane and Manchester Victoria, all by December 2014

Phase 3: Preston to Blackpool, by May 2016

Phase 4: Manchester Victoria to Preston (Euxton Junction), by December 2016

Phase 5: Manchester Victoria to Stalybridge, Guide Bridge to Stalybridge, December 2016

Tell us what you think – have your say below or email opinion@railtechnologymagazine.com

Comments

Pedr Jarvis   08/11/2014 at 19:13

Where were the unexpected ground conditions, please? Couldn't be Chat Moss, could it?

RTM   10/11/2014 at 08:36

We're still trying to get to the bottom of that one Pedr! (Let's hope not though...)

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

22/03/2019Government gives ‘hugely important’ £208m Belfast Transport Hub the green light

A new £208m Belfast Transport Hub with major rail and bus connections has been granted planning permission by the Department of Infrastruct... more >
New to-the-minute measures for train punctuality introduced to tackle delays

22/03/2019New to-the-minute measures for train punctuality introduced to tackle delays

New measures of train punctuality are to be released by train operators and Network Rail next month in a bid to improve performance. The Rai... more >
FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

22/03/2019FirstGroup finalises £100m order for Hitachi trains as plans for London-Edinburgh rail link move forward

FirstGroup has finalised a £100m order for Hitachi AT300 electric trainsets in a partnership between the two companies to create a new Lond... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Women in rail - is the industry on the right track?

12/03/2019Women in rail - is the industry on the right track?

RTM sits down with Samantha Smith, sole female member of the TransPennine Route Upgrade Alliance Leadership Team, to find out more about encourag... more >
TfN Strategic Transport Plan: not just for transport's sake

22/01/2019TfN Strategic Transport Plan: not just for transport's sake

Peter Molyneux, Transport for the North’s (TfN’s) strategic roads director, has been leading on the development of the seven economic... more >
Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

22/01/2019Exclusive: Midlands Connect and WMRE talk collaboration and investment in the Midlands' railway

In the jigsaw puzzle of regional transport decision-making, there must be collaboration and compromise. Midlands Connect media lead James Bovill ... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

The West Midlands 30-year strategy

19/03/2019The West Midlands 30-year strategy

Malcolm Holmes, executive director of West Midlands Rail Executive (WMRE), outlines the West Midlands Rail Investment Strategy 2018-2047. Th... more >
read more blog posts from 'the sleeper' >

comment

26-30 Railcard: taking advantage of opportunities

19/03/201926-30 Railcard: taking advantage of opportunities

After a nine-month national trial, the rail industry launched its seventh National Railcard for 26-30-year-olds on 2 January 2019. Rail Delivery ... more >
Caledonian Sleeper: a railway icon re-imagined

19/03/2019Caledonian Sleeper: a railway icon re-imagined

The world-renowned Caledonian Sleeper, due to begin operations at the end of spring 2019, completed its first Scotland to London journey earlier ... more >
East West Rail: the next steps

19/03/2019East West Rail: the next steps

In January, five route options for the central section of East West Rail were published as part of a public consultation on the next phase of the... more >
Rail's role in transit-orientated developments

19/03/2019Rail's role in transit-orientated developments

Jonathan Bray, director at the Urban Transport Group (UTG), argues that transit-oriented developments are the future – and that rail has a ... more >