Latest Rail News

07.04.16

Gospel Oak to Barking Line to close for eight months for electrification upgrades

Closures on the Gospel Oak to Barking Line are due to start from June to allow for electrification upgrades.

From 4 June to 25 September the South Tottenham to Barking line will close and the South Tottenham to Gospel Oak line will only run at weekends, and the full Gospel Oak to Barking line will then close from 26 September to February 2017. TfL will provide a replacement bus service.

Once complete, the upgrades will allow TfL to run four-carriage electric trains instead of the current two-carriage diesel models from January 2018.

Richard Schofield, Network Rail’s route managing director, said: “This investment will transform the service on this route, doubling capacity with cleaner, quieter electric trains and is a key element of our wider Railway Upgrade Plan.”

The improvement works will include installing overhead wires, building three new switching stations, lowering four sections of track, rebuilding four bridges and modernising six, and lengthening platforms and enhancing stations to accommodate longer trains.

Network Rail has been working on the foundations for the structures that will carry the overhead wires since October. The scheme is being funded by £25m from TfL and £90m from the DfT.

The National Infrastructure Commission said in a recent report that extensive investment in London’s railways, including Crossrail 2, is needed to accommodate the growing population of the capital, which will become a ‘megacity’ of 10 million people by 2033.

To keep members of the public updated about the closures, TfL and Network Rail are organising drop-in sessions at the affected stations and sharing information via e-mail alerts, Twitter, posters and station announcements.

Mike Stubbs, TfL’s director of London Overground, said: “We recognise that there will be disruption to customers while the upgrade work is carried out and I'd like to thank them for their patience in advance.”

He said that TfL would work with Network Rail to try to reduce the closure period.

Comments

Andrew Gwilt   07/04/2016 at 23:43

Plus the electrification to Barking could also kick start the London Overground extension to Barking Riverside and even to Abbey Wood if necessary. The electrification could be completed by late February or early March next year if it doesn't get held up.

GW   09/04/2016 at 22:39

Another example of lazy engineering by Network Rail. No thought about those who use the route everyday and the inconvenience caused to the users.

Paul   11/04/2016 at 15:12

@Andrew Gwilt Abbey Wood isn't going to happen anytime soon, as the nowagreed barking riverside extension design has no provision for it, and will require a complete demolition and rebuild to make a river crossing possible.

Andrew Gwilt   13/04/2016 at 09:33

Properly DLR extension could be extended to Abbey Wood & Dagenham Dock would be ideal as London Overground extended to Barking Riverside would be the terminus of the London Overground GOBLIN (Gospel Oak-Barking line) or to be renamed as GOBRLN (Gospel Oak-Barking Riverside line) once the extension to Barking Riverside is completed.

John Barnes   04/05/2016 at 08:10

This is completely unacceptable. You can't close an entire line for 6 months. There are many other options, including a shuttle line along the stations which are currently not being worked on. This is lazy and poorly thought out.

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

19/11/2018Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

Errors made during the derailment of a London Waterloo train last year showed lessons learned from the 1988 Clapham Junction disaster were &ldquo... more >
Wales and Borders rail to receive £2bn government funding

19/11/2018Wales and Borders rail to receive £2bn government funding

Network Rail Wales and Borders has announced £2bn in government funding to be spent on a project to maintain and renew the Wales and Border... more >
HS2 kicks off the bid race to build Curzon Street station

19/11/2018HS2 kicks off the bid race to build Curzon Street station

HS2 has announced the start of its search for contractors to build its new £435m Curzon Street station. Around four contractors will b... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Finding positives in negative short-circuiting devices

09/11/2018Finding positives in negative short-circuiting devices

Sponsored interview  Anything that brings about safety and time-saving benefits is a valued improvement for the rail industry, which is w... more >
Taking to the skies

30/10/2018Taking to the skies

Network Rail’s commitment to driving innovation is best encapsulated by its latest scheme involving high-definition imagery drones, or UAVs... more >
Going global: an interview with Network Rail’s Leevan Finney

29/08/2018Going global: an interview with Network Rail’s Leevan Finney

RTM’s Jack Donnelly sat down with one of the leading minds behind Network Rail’s most advanced and innovative rail maintenance techno... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

Elizabeth Line: short-term pain for long-term gain?

13/11/2018Elizabeth Line: short-term pain for long-term gain?

Tim Bellenger, director of policy and investigation at London TravelWatch, discusses the deferred opening of the central section of the Elizabeth... more >
read more blog posts from 'the sleeper' >

comment

Challenging the perceptions of rail

13/11/2018Challenging the perceptions of rail

Darren Caplan, chief executive of the Rail Industry Association (RIA) explains how the RIA Rail Fellowship Programme is challenging people’... more >
Data-driven rail

13/11/2018Data-driven rail

Andy Cross, director of Elastacloud, and Lucy Bealing, from the Elastacloud Rail Centre of Excellence, discuss their innovative collaboration wit... more >
Looking ahead to the Williams Review

13/11/2018Looking ahead to the Williams Review

Darren Shirley, chief executive of the Campaign for Better Transport, takes a look at the government’s root and branch review of the rail s... more >
Digital Railway: All change on the ECML

06/11/2018Digital Railway: All change on the ECML

Network Rail route programme director, Toufic Machnouk, explains why only a radically new approach to contracting will deliver a better service f... more >