Latest Rail News

07.05.15

Ground decontamination delays Bromsgrove station relocation

Resignalling work and the relocation of the new station at Bromsgrove have been delayed, but the overall project timescale will still be met, RTM has been told. 

Barnt Green to Bromsgrove electrification, which is part of a £100m investment in the railway in north Worcestershire, will significantly improve local rail services once complete. 

Work is progressing on the structures clearance at Barnt Green and in parallel the construction of a new railway station at Bromsgrove has been taking shape – but is now delayed. 

Richard Dugdale, Network Rail’s project sponsor, told RTM that the relocation is a “considerable undertaking”. The original completion date was May 2015 but this won’t happen. 

The station project is a third party scheme, promoted by Centro and Worcestershire County Council, being delivered by Network Rail. Work started on the new site, 450m south of the existing Bromsgrove station, last year. 

bromsgrove artist's impression hi-res

“But we’ve encountered issues there, principal of which is that [the need for] ground decontamination is more extensive and onerous than the trial pits would have led us to believe,” said Dugdale. 

“It is a difficult site, as it is on the site of an old locomotive depot and a more recent large oil terminal. There are some considerable contamination issues and that decontamination work, which is probably four times bigger than predicted, is just concluding. 

“This has involved a deep dig and the removal of spoil and the replacement with clean fill, mostly in the area that will be the new car park.” 

The date for the station opening is now November 2015, but that delay does not matter in output terms, Dugdale said. “The new and the old will continue to service the existing level of timetable up until the December 2016 timetable change, which is when the electrics come in.” 

As well as delaying the station relocation, Network Rail has deferred a 12-day closure in late October for the new signalling system to be installed between Ashchurch (Cheltenham) and Five Ways, to be brought into use on 2 November. 

Part of the project, needed to electrify the line, is that the existing signalling equipment between Barnt Green and Bromsgrove requires immunisation works, which will result in a complete signalling renewal and control transfer to the West Midlands Signalling Centre.

“We are not going to commission in November; it’ll be next year,” said Dugdale. “The main reason for this is that the readiness reviews indicate that a level of risk associated with the November commissioning which we won’t accept. 

“We are deliberately re-planning and allowing the resignalling project more time and deferring what was a sizeable closure of the route through Bromsgrove – not just for resignalling.” 

Network Rail has a regulatory requirement to have Barnt Green to Bromsgrove energised by July 2016. 

Dugdale told us: “We are still working to this schedule. However, we are currently in negotiation with train and freight operators about the access requirements for the signalling commissioning. I can’t say any more than that, other than it will be early 2016.” Despite the deferrals, he is confident the project will be delivered on time. 

To learn more about the Barnt Green to Bromsgrove electrification project and for the full interview with Richard Dugdale read the April/May 2015 edition of RTM which is now available for FREE using the new RTM App, available on iOS and Android. Search ‘RTM Magazine’ in the App Store / Google Play. 

Comments

There are no comments. Why not be the first?

Add your comment

 

related

rail technology magazine tv

more videos >

latest rail news

Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

19/11/2018Clapham Junction disaster lessons are ‘fading’ from rail industry following London Waterloo collision last year, RAIB finds

Errors made during the derailment of a London Waterloo train last year showed lessons learned from the 1988 Clapham Junction disaster were &ldquo... more >
Wales and Borders rail to receive £2bn government funding

19/11/2018Wales and Borders rail to receive £2bn government funding

Network Rail Wales and Borders has announced £2bn in government funding to be spent on a project to maintain and renew the Wales and Border... more >
HS2 kicks off the bid race to build Curzon Street station

19/11/2018HS2 kicks off the bid race to build Curzon Street station

HS2 has announced the start of its search for contractors to build its new £435m Curzon Street station. Around four contractors will b... more >

editor's comment

23/01/2018Out with the old...

Despite a few disappointing policy announcements, especially for the electrification aficionados amongst us, 2017 was, like Darren Caplan writes on page 20, a year generally marked by positive news for the rail industry. We polished off the iconic Ordsall Chord (p32), hit some solid milestones on Thameslink (p40), progressed on ambitious rolling stock orders (p16), and finally started moving forward on HS2 (p14) ‒ paving the way for a New Ye... read more >

rail industry focus

View all News

interviews

Finding positives in negative short-circuiting devices

09/11/2018Finding positives in negative short-circuiting devices

Sponsored interview  Anything that brings about safety and time-saving benefits is a valued improvement for the rail industry, which is w... more >
Taking to the skies

30/10/2018Taking to the skies

Network Rail’s commitment to driving innovation is best encapsulated by its latest scheme involving high-definition imagery drones, or UAVs... more >
Going global: an interview with Network Rail’s Leevan Finney

29/08/2018Going global: an interview with Network Rail’s Leevan Finney

RTM’s Jack Donnelly sat down with one of the leading minds behind Network Rail’s most advanced and innovative rail maintenance techno... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. ... more > more last word articles >

'the sleepers' daily blog

Elizabeth Line: short-term pain for long-term gain?

13/11/2018Elizabeth Line: short-term pain for long-term gain?

Tim Bellenger, director of policy and investigation at London TravelWatch, discusses the deferred opening of the central section of the Elizabeth... more >
read more blog posts from 'the sleeper' >

comment

Challenging the perceptions of rail

13/11/2018Challenging the perceptions of rail

Darren Caplan, chief executive of the Rail Industry Association (RIA) explains how the RIA Rail Fellowship Programme is challenging people’... more >
Data-driven rail

13/11/2018Data-driven rail

Andy Cross, director of Elastacloud, and Lucy Bealing, from the Elastacloud Rail Centre of Excellence, discuss their innovative collaboration wit... more >
Looking ahead to the Williams Review

13/11/2018Looking ahead to the Williams Review

Darren Shirley, chief executive of the Campaign for Better Transport, takes a look at the government’s root and branch review of the rail s... more >
Digital Railway: All change on the ECML

06/11/2018Digital Railway: All change on the ECML

Network Rail route programme director, Toufic Machnouk, explains why only a radically new approach to contracting will deliver a better service f... more >