TOC bosses appear before MPs, blame chaos on infrastructure failures

Bosses from Govia Thameslink Railway (GTR) and Northern Rail cited failures in infrastructure being completed in time and last-minute changes to timetables as reasons for a chaotic bedding in of new timetables that led to delays and cancellations last month.

Speaking to the transport select committee yesterday, David Brown and Rob Warnes of Northern Rail and Nick Brown and recently-resigned Charles Horton from GTR claimed that changes to timetable details were “not clearly understood” of the impact it would have on the implementation of the new timetable on 20 May.

“There is no single cause of what has happened here,” said Horton. “This has been a systemic failing of the industry's timetabling system which has had devastating consequences on our customers and we are very, very sorry for that.”

Last week statistics from the Office of Rail and Road (ORR) announced that passenger journeys in 2017-18 fell for the first time in eight years.

GTR, who have been one of the most highly-publicised providers forced to delay and cancel trains during the tumultuous implementation of the new timetable, suffered a second successive year where passenger numbers fell. Chief executive Charles Horton resigned citing “huge frustration” from passengers last week.

Speaking to the transport select committee, Horton claimed that heavy delays to the finalisation of the timetables — nine weeks later than it was originally planned to be finalised — was caused by “extremely protracted and a complicated number of changes that happened during the timetable process.”

Horton continued to say that changes late changes the timetables had a knock-on effect across the five other providers, whose timetable had to liaise with GTR, citing issues such as the number of drivers, and the skill and knowledge of those drivers on new routes only had knowledge of new timetables by April, which ultimately left to cancellations and delays that are still ongoing.

“I’m terribly sad and terribly sorry that it’s ended the way it has, and our job now is to take the situation we’re in at the moment and get it back on track as soon as we possibly can do,” Horton added.

'The upgrade for people clearly wasn't delivered'

Northern boss David Brown said infrastructure failures, such as the failure to electrify the lines between Blackpool, Preston, and Manchester meant that the new timetables could not be implemented smoothly last month.

Brown went on to say that, due to the late decision that the electrification of the line would not be completed in time, the operator only had 16 weeks to plan for the new timetable, as opposed to the full 40 weeks preferred to ensure a complete and full implementation of the schedules.

“The timetable change that was supposed to be a significant upgrade for people in the north of England clearly wasn’t delivered,” said Brown.

The chief executive of Northern Rail went on to say that the provider requested for the timetable to be “rolled forward” to later in the year, after being notified that certain infrastructures like the electrification of lines in the north west would not be completed in time, but added that the majority of operators wanted to keep the implementation date in May.

“A significant number of other players didn’t want that to happen and that option was not the preferred option,” Brown told the committee.

“We’ve apologised to our customers many times before and we would like to do so again today. We’re truly sorry the timetable and service provided in the first two weeks of the timetable clearly affected people travelling to and from work but also major life events as well.”

Brown noted that it was only on 18 May that the industry realised they would see “the full ramifications” of the struggled timetable implementation.

Earlier this month transport secretary Chris Grayling commissioned an ORR-led inquiry into the chaotic timetable embedding across the UK. ORR Chair Stephen Glaister will lead the inquiry.

Enjoying RTM? Subscribe here to receive our weekly news updates or click here to receive a copy of the magazine!

Comments

There are no comments. Why not be the first?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the... more > more last word articles >

'the sleepers' daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >