Inbox

20.10.15

NR overspending on renewals but delivers ‘less than expected’

Network Rail spent £324m (12%) more on renewals during 2014-15 than the ORR signed off on, but has delivered “less than expected”. 

In its ‘Annual efficiency and finance assessment of Network Rail 2014-15’ report, the ORR (Office of Rail & Road) said that higher renewals cost were the main reason for driving up Network Rail’s total expenditure to £10.2bn – £148m (1.5%) higher than the PR13 financial assumption. 

The renewals overspend came despite deferring renewals work of a net £420m to later in CP5. 

“This significant overspend of £744m was largely due to higher unit costs on assets such as track and signalling, where there were some supply chain issues,” said the ORR.

Renewal cost

It was noted that renewals financial underperformance* of £186m was affected in track (£86m) due to unit costs being “adversely affected by technical problems with new high output equipment” and cost impacts from changes to the procurement framework. 

Signalling, which saw a £37m underperformance, was affected by cost increases and added scope for certain large schemes such as Watford, Wolverhampton, Cardiff and Bristol. And in civils (£22m) there were cost overruns on a number of projects, including additional costs resulting from “adverse weather events”. 

Maintenance underperformance stood at £79m, which included £37m on the Tidy Railway programme to reduce litter; and schedule 8 payments to train operators were £105m higher than assumed. 

Enhancements underperformance was £47m mainly due to Thameslink (London Bridge) and increasing costs on the Great Western electrification programme, Birmingham New Street and West Coast Power Supply upgrade. 

In 2014-15 Network Rail’s support, operations, maintenance and renewals efficiency deteriorated by 2.3% overall. This was largely driven by the rising cost of renewals, which pushed renewals efficiency down by 9.1%.

Overall

Six routes spent more than the ORR assumed in PR13 and four routes spent the same or less. In percentage terms the Anglia and Wessex routes had the largest variances compared to PR13 due to overspends on track and civils, and also on signalling for the Anglia route. 

The largest routes, London North East (LNE) and London North West (LNW), also had significant variances mainly on track and also signalling for LNW. Scotland and Western spent less than the ORR’s assumption, but this was due to deferrals of particularly large signalling projects on these routes.

Route renewals

On track renewals, the largest variances were in the East Midlands and LNW and LNE routes. In East Midlands off-track works costs were higher than expected in order to maintain asset quality and functionality. In LNW the variance was due to “expected contractor savings not materialising, planned efficiencies from improved working practices not yet yielding the benefits it expected and costs on the Watford re-signalling programme were higher than anticipated”. 

In seven routes civils renewals were higher than the ORR’s PR13 assumptions and in three routes civils renewals expenditure was below our PR13 assumptions.

322 Signalling

During the period, Network Rail spent £2.919bn on enhancements to the network, which was £64m less than the ORR’s estimates. However, the determination was a provisional sum because a number of projects were at an early stage of development at that time. 

The ORR added that looking ahead to the remainder of CP5, there are “considerable affordability challenges” for Network Rail on enhancements. 

“For example, we have only completed Enhancement Cost Adjustment Mechanism (ECAM) reviews on some 50% of the current ECAM portfolio (by SBP value), but the efficient funding we have determined already adds up to about 80% of the total assumed in the determination,” it noted. 

Due to the significant number of enhancements milestones missed so far this control period, the ORR decided that Network Rail is in breach of its licence. However, as reported last week by RTM, the regulator has concluded that the company is already “taking action” to improve the planning and delivery of its CP5 enhancements programme. 

* Financial performance compares Network Rail’s income and expenditure to the PR13 determination. If Network Rail can demonstrate that it has spent less whilst delivering its outputs then it can claim financial outperformance. Network Rail needs to show that it has not spent less by non-delivery of outputs or by simply deferring work or working in an unsafe or unsustainable way. If it spends more it is financially underperforming. This measure has replaced Financial Value Added (FVA), which was used in CP4. (Source: ORR) 

Comments

Lutz   21/11/2015 at 12:17

Despite the announcements on infrastructure spending over the last year, we should probably anticipate a reduction, or real-value freeze in the overall funding of rail projects due to both the problems with NR's poor delivery - which is unlikely to be resolved in this CP - and the rapid change in the headwinds in the debt markets. In short, the funding of projects is likely to dry up unless the private sector finds sufficient value in individual projects. I would expect this bodes worse for the provincial 'me-too' projects that do not have a sound business case in the first place than the high density, high BCR projects for London and its hinterland.

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

HS2 Ltd: Five tech firms join Innovation Accelerator initiative

11/09/2020HS2 Ltd: Five tech firms join Innovation Accelerator initiative

HS2 Ltd have announced today (11 Sept) the first five revolutionary tech firms that will join HS2 Ltd’s Innovation Accelerator programme. ... more >
Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >
GTR spreads messages of support on Suicide Prevention Day

10/09/2020GTR spreads messages of support on Suicide Prevention Day

As today (10 Sept) mark the annual World Suicide Prevention Day, Govia Thameslink Railway (GTR), have revealed ‘Affirmation Art’ clus... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News