Inbox

07.08.15

Exclusive: Project delivery problems 'systemic' at Network Rail – ORR

Weaknesses in Network Rail’s project development and delivery are “systemic” and the infrastructure owner may be in breach of its licence as regards the delivery of its enhancement programmes, according to the Office of Rail and Road (ORR). 

In a letter sent to NR, the DfT and Transport Scotland, Alan Price, the ORR’s director of railway planning and performance, outlined the preliminary findings of the regulator’s investigation into whether NR had “done everything reasonably practicable to meet its licence obligations in relation to achieving its regulated outputs for CP5”. 

He said: “Having carried out this work, our preliminary view is that NR may not have done, and is not doing, everything reasonably practicable to comply with condition 1 of its network licence in relation to the delivery of its enhancements programme.” 

Price highlighted that given the early life-cycle status of much of the CP5 portfolio the ORR could not expect NR to set completion milestones, however the regulator’s focus on the timely delivery of GRIP 3 gives an “early indication of the level of stress in the programme”.

He added that NR missed 16 of 44 (36%) GRIP 3 regulated outputs and 14 out of 40 (35%) GRIP 6 regulated outputs in 2014-15. These 30 missed milestones were on projects that vary by size, type, location and complexity. 

ORR and NR analysis has thrown up some particular weaknesses: 

  • Poor setting of project requirements (front-end definition) with inadequate change control against a baseline;
  • Inadequate governance and challenge of projects as they pass through development gateways;
  • Inconsistent consideration of safety issues during design and optioneering;
  • The accountabilities of the client, sponsor and deliverer are blurred, as projects move through their lifecycle;
  • Cost estimation and risk functions are not adequately resourced or governed through the early project lifecycle;
  • No defined framework, tools and techniques for managing complex infrastructure programmes resulting in underestimates of timescales, costs and impact on operational performance;
  • Absence of portfolio management capability to validate project reporting in terms of cost and schedule, for example by peer reviewing and challenging projects to provide early warning of failure or by better identification of shortages in critical resources;
  • Late requirements identified when handing asset over to operator;
  • Land and consents issues underestimated;
  • Unknown asset condition, resulting in late increases to scope and replanning;
  • Productivity is lower than planned;
  • Weak assurance of compliance with safety legislation and standards;
  • Inadequate and late technical files for authorisation under interoperability regulations. 

Price said: “We consider that the wide range of identified weaknesses indicates that NR's project development and delivery weaknesses are systemic, rather than the result of individual project failings or adverse circumstances. This is also evidenced by the wide range of causes and the scale of the required long-term improvements that NR needs to develop and embed into its business.” 

He added that NR’s response to the regulator’s concerns had been “slow, localised and patchy”, but began to be properly coordinated in February 2015 by the initiation of a review led by one of NR’s non-executive directors – Malcolm Brinded – who now chairs a specially convened task force known as the Major Projects Delivery Committee (MPDC). 

Price noted that during the course of the investigation, NR has presented several iterations of its Enhancements Improvement Plan (EIP). The EIP has been produced under the auspices of the MPDC and is designed to draw together a range of cross-NR actions to improve its capability and address ORR’s concerns. 

However, at the time of the ORR’s assessment, the EIP still had “omissions” and “underdeveloped actions”, particularly NR’s authorisation submissions, its approach to improving on ‘safety by design’ and its ability to manage major infrastructure programmes with timetable performance risks. 

The ORR also noted that it has “not seen clear analysis” of the causes of missed milestones with a link to the associated actions in its plan. 

“We therefore do not have complete confidence that NR has yet identified every issue,” said Price. “On the basis of our findings, we cannot be satisfied that NR is doing everything reasonably practicable to achieve its regulated outputs, until: the EIP is sufficiently finalised; and there is evidence of improvement following effective implementation of the finalised EIP.” 

NR has been invited to make further representations to the ORR by 1 September 2015, after which the ORR will decide whether a licence breach has taken place. This is likely to be at the ORR board’s next meeting in September. 

Responding to the letter in a statement sent to RTM, Francis Paonessa, managing director infrastructure projects at NR, said: “Since 2009, Network Rail has successfully delivered over 5,000 projects worth more than £15bn. The projects set before us for our current five-year funding period to 2019 were bigger and more complex than ever and required a step-change in delivery – both for the company and its supply chain. 

“Despite this challenge, over three-quarters of our regulatory project milestones have been delivered to time or within weeks of target. But we know we can and must do better which is why, earlier this year, we set up a special Board-led task force to strengthen our major project delivery. The task force has produced a detailed improvement plan that is already underway and good progress is being made.”

A DfT spokesperson added that it is “entirely right” that the regulator should hold Network Rail to account through this ongoing investigation. “As we have previously announced, the secretary of state has asked Dame Colette Bowe to look at the lessons learned from Network Rail’s enhancements programme and she will report back in the autumn.”

(Image: c. Stefan Rousseau)

Comments

Wimg   07/08/2015 at 12:18

What an impressive report ! Public Company Network Rail is now filleted to the bare bones , Mr McLoughlin has something to mesmerize .. Talking about rules and regulations ... , at least it's not the European Union here to put the blame on

Lutz   07/08/2015 at 20:41

This has all been evident for some time, but I have never heard of a committee being an appropriate response. What is NR going to to ensure it has the people with the right skills, and what is it going to do with the current bunch of under performers?

Add your comment

related

rail technology magazine tv

more videos >

latest rail news

Network Rail publish Decarbonisation Plan

11/09/2020Network Rail publish Decarbonisation Plan

Network Rail have released their interim Traction Decarbonisation Network Strategy, illustrating its preliminary recommendations for decarbonisin... more >
Trains kept moving by AWC despite damaged overhead wires

11/09/2020Trains kept moving by AWC despite damaged overhead wires

Avanti West Coast have taken an unlikely option to allow their timetable to run, without delays, despite damaged overhead wires. The operato... more >
GTR spreads messages of support on Suicide Prevention Day

10/09/2020GTR spreads messages of support on Suicide Prevention Day

As today (10 Sept) mark the annual World Suicide Prevention Day, Govia Thameslink Railway (GTR), have revealed ‘Affirmation Art’ clus... more >
Transport Secretary commits to a resilient railway

10/09/2020Transport Secretary commits to a resilient railway

Network Rail’s provisional report on the Stonehaven tragedy, commissioned by the Transport Secretary Grant Shapps immediately after the eve... more >

last word

Encouraging youngsters to be safe on the railway

Encouraging youngsters to be safe on the railway

This summer, Arriva Group's CrossCountry and the Scout Association joined to launch a new partnership to promote rail safety among young people. Chris Leech MBE, business community manager at the TOC, gives RTM an update on the innovative scheme... more > more last word articles >

interviews

Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

24/06/2019Andrew Haines, CE of Network Rail, tells BBC News his organisation could issue future rail franchises

Andrew Haines, the Chief Executive of Network Rail, has told the Today programme on Radio 4's BBC’s flagship news programme that he wo... more >

the sleeper's daily blog

On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

29/06/2020On the right track, Sulzer is awarded RISAS accreditation for Nottingham Service Centre

Following an independent audit, Sulzer’s Nottingham Service Centre has been accepted as part of the rail industry supplier approval scheme (RISAS). The accreditation reinforces the high-quality standards that are maintained by Sulzer’s network of independent repair facilities across the UK and further afield in its global network. ... more >
read more blog posts from 'the sleeper' >

comment

The challenge of completing Crossrail

05/07/2019The challenge of completing Crossrail

With a new plan now in place to deliver Crossrail, Hedley Ayres, National Audit Office manager, major projects and programmes, takes a look at ho... more >
Preparing the industry to deliver trains for the future

04/07/2019Preparing the industry to deliver trains for the future

The move to decarbonise the rail network involves shifting to cleaner modes of traction by 2050. David Clarke, technical director at the Railway ... more >
Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

02/07/2019Sunshine future beckons for South Wales Railways, says 10:10 Climate Action’s Leo Murray

Smart electrification is the way to boost clean energy resources, argues Leo Murray, director at 10:10 Climate Action. Contractors are clear... more >
Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

02/07/2019Ambition doesn’t have to be expensive, says Midland Connect's Maria Machancoses

The TCR Midlands conference is only days away and tickets are going fast for the sector event of the year at the Vox Conference Centre in Birming... more >

rail industry focus

View all News